The CEI will review the as-built plans submittal to verify accordance with the Department’s latest FDOT Design Standards 2016, and Plan Preparation Manual, 2015, and Construction Project Administration Manual (CPAM), 2016, for “As-Built”
contract documents.
The CEI must review the as-built plan deliverables and verify them against the CEI’s Master Record maintained
throughout construction. If the auditor finds errors or omissions, the as-built plan fails. The CEI indicates the errors on the plans and sends it back to the contractor for corrective action. Submit passing deliverables to the FDOT project engineer
with the recommendation for acceptance.