District Five Consultant Project Management Schedule Dictionary
Activity Code | Activity Description (Public Site) | D2 Description | Predecessor | Successor | Description of AE from Template Definitions |
100 | LOCATION HYDRAULICS REPORT-LHR | | |||
101 | TASK WORK ORDER AUTHORIZATION | | |||
102 | TRAFFIC STUDIES | | |||
103 | BASELINE CONTROL SURVEY | Baseline Survey Work | 250-Begin Work; | 106-Design Survey Work | Establish Horizontal and Vertical Control, Locate pertinent existing monumentation to establish alignment, and Set alignment monumentation |
104 | ENGINEERING REPORT | | |||
105 | PHOTO TOPOGRAPHICS | | |||
106 | DESIGN SURVEY | Design Survey Work | 103-Baseline Survey Work 25401-Design Survey Wk Requested | 108-Final Design Survey Approved 31501-Prepare 60% Control Maps | Locate all existing topographic features along the alignment, usually covering the entire corridor from Right-of-Way to Right-of-Way as directed by the Department and the Engineer of Record. |
107 | DESIGN BUILD | | |||
10701 | Prepare DRAFT RFP | | |||
10702 | Prepare FINAL RFP | | |||
108 | PLOT DESIGN SURVEY | | |||
10801 | Final Design Survey Approved | 10601 - Design Survey Work 30402 - Pavement Data Received | 11301 - Prepare PH I Plans 27101 - Request Geotechnical Information | Once the survey is reviewed for compliance with all survey guidelines and standards, it is place on the CAiCE Server and the engineer of record is notified | |
109 | DRAINAGE DESIGN | | |||
110 | TRAFFIC SIGNAL PLANS | | |||
111 | SIGNING SYMBOL PLANS | | |||
112 | RDWY LIGHTING PLANS | | |||
113 | ROADWAY PLANS | Prepare Roadway Plans | | ||
11301 | ROADWAY PLANS | Prepare Phase I Plans | 10801 - Final Design Survey Approved | 90101 - SUBMIT PH I PLANS | The preparation of PH I Plans consist of identifying all R/W needs, wetland permits (needed for shoulders or drainage work), location of all utility poles in the clear zones, geotechnical issues, guard rails, bridge rail; location of any other potential conflicts and evaluation of all critical elements; review super-elevation and transitions with smart level and identify any areas that need an exception or variance. After all conflicts have been identified, the scope package is sent out. All details need to be included for scope. A copy of the pavement design, scope, typical data package and scope plans are placed on the electronic plans submittal website. A list of conflicts to be addressed is also provided to Utilities. Specs is also informed of any TSP's and MSP's needed for the project |
11302 | ROADWAY PLANS | Prepare Phase II Plans | 19902 - Review LRE Unit Price - PH I | 16300 - IDENTIFY MA NEED 90201 - SUBMIT PH II PLANS 44501 - IDENTIFY R/W TRANSFER NEED | Resolve all issues brought out on Scope review; start signing and pavement markings and sign inventory, convert LRE Estimates to Transport and load in all the updated quantities for pricing, coordinate with Geotech for boring information, structures for bridge railing details, utilities for issues from scope, and local officials on request/comments from scope; Provide a copy of the plans to all necessary parties and schedule review at field location |
11303 | ROADWAY PLANS | Prepare Phase III Plans | 19903 - Update LRE Quantities - PH II 30201 - Review PH II Plans | 26402 - Submittal II to Utilities 90301 - SUBMIT PH III PLANS | Resolve all issues brought out in PH II review, document the issues and responses and file with the PH II documents, estimate any project cost adjustments from the changes to the PH II for approval, complete the design work including pavement markings, signal, geotechnical work, structures work, utilities, and any other component; load transport and complete comp book, update estimate to include work day items, coordinate with District Construction for contract time, insure all utility and permit issues are clear, get final details from Geotech and structures if required, using EDI to create .pdf of plans; provide a copy to all components; Submit TSP's to Specs for review |
11304 | ROADWAY PLANS | Prepare Phase IV Plans | 19906 - Review Trnsport Unit Prices - PH III 30301 - Review PH III Plans | 19907 - Update Trnsport Quantities - PH IV 90401 - SUBMIT PH IV PLANS | Resolve all PH III Issues; documents the issues and responses and file with PH III documents. Clean up plans and comp book for submittal; sign and seal electronically the project delivery CD. Include the specs submittal document found on ERC; Let specs know of any TSP's and MSP's that will be needed for the project. Address all of the specs comments and document the changes for the final delivery. |
114 | BRIDGE HYDROLICS RECOMM | | |||
115 | BRIDGE PLANS | | |||
11501 | BRIDGE PLANS | Prepare 30% Structure Plans | | An abbreviated version of the Bridge Development Report used to define the continuing structure work and detail of justification for the proposed bridge type within the project limits; the 30% Roadway Plans and the BDR are normally submitted together | |
11502 | BRIDGE PLANS | Prepare 60% Structure Plans | 23403-NTP 25001 - Begin Work | 26401 - Submittal I to Utilities 90201-Submit 60% Structure Plans | Plans consisting of the Substructure Submittal required for all bridge projects and the 60% Structure Plans submitted for primarily Category I Structures and some Category II Structures; all comments from the 30% submittal / BDR should have been resolved; this phase should also include details applicable to final concrete outlines, major reinforcing steel, and various addition detailed components relative to bridge development |
11503 | BRIDGE PLANS | Prepare 90% Structure Plans | 19904 - Review LRE Unit Price - PH II 90801-Response to 60% Comments 90201-Submit 60% Structure Plans 30101-60% Structure Plans/MSP's/TSP's 24501 - FINAL BIDABILITY REVIEW | 26402 - Submittal II to Utilities 91301-Submit 90% Strucutre Plans | Plans submitted as 90% reflecting that all previous phase comments have been resolved to include prints of the completed plans, summary of Pay Items with Quantities, design calculation, final PH II Geotechnical Report, Addendum to Hydraulic Report and Technical Special Provisions, if applicable. All sheets and details should be included at this stage |
11504 | BRIDGE PLANS | Prepare 100% Structure Plans | 19906 - Review Trnsport Unit Prices - PH III 90802-Response to 90% Comments 30201-Review 90% Plans and Specs | 90411-Prepare Final Plans 91401-Submit 100% Structure Plans | Following resolutions to any 90% comments, the EOR makes all authorized changes to the plans and Technical Special Provisions and submits to the Specifications office |
116 | SCOUR ANALYSIS | | |||
117 | RIGHT OF WAY PARCEL VACATE | | |||
118 | REVIEW BRIDGE PLANS | | |||
119 | CONCEPT REVIEW | R/W CONCEPT REVIEW | 13902 - Submit 60% R/W Maps | 13903 - Prepare 90% R/W Maps (FF) | Discuss with the R/W Coordinator to ensure all parcels are reviewed and all issues are addressed |
120 | APPRAISALS | 20801 - Appraisal Contract | 14301 - Appraisal Review (SS+30) | The period of time allotted for the submission of all real estate appraisals required for the initial negotiation of the identified right-of-way project; Starts when the appraiser receives his first NTP/LOA / Finishes when the appraiser delivers his last initial negotiations appraisal for review | |
20012 | PLANNING CONSULTANT ADVERTISEMENT | | |||
20032 | DESIGN CONSULTANT ADVERTISEMENT | | |||
201 | PLANS COMPLETED | | |||
202 | POST DESIGN SERVICES | | |||
203 | C.E.I. CONS. CONT. EXEC. | | |||
374 | CONSULTANT CONTRACT EXPIRATION | | |||
375 | CONSTRUCTION CLEAR DATE | | |||
376 | ENVIRONMENTAL CLEAR/CERTIF | 90301 - SUBMIT PH III PLANS | 20401 - PRODUCTION DATE | ||
377 | ITS DESIGN | | |||
378 | ITS SUBMITTAL | | |||
379 | ITS REVIEW | | |||
121 | NEGOTIATION | 12401 - Relocation Needs Assessment | 12201 - CONDEMNATION 27301 - FINAL R/W ORDER OF TAKING | The time period for presenting offers and negotiating with property owners/representatives to purchase right of way parcels. The initial offer is based on approved compensation determined by the review appraiser. The r/w agent attempts to negotiate a settlement agreement that will allow the parcel to be closed without condemnation. The negotiation end date is the date of the final order of taking for the project; Starts when a first offer is made on a parcel other than a TIITF (if all parcels are TIITFs, the start date is request date to DEP) / Finishes when the last parcel is acquired | |
122 | CONDEMNATION | 12101 - NEGOTIATIONS 12901 - RELOCATION (SS+130) | 25501 - R/W CERTIFIED 38001 - PRODUCTION READY | 1st suit package to Legal 20 days after the Final OT; Starts when the first suit on the project is filed / Finishes when the last Date of Deposit is made | |
123 | R/W DEMO CONTRACT | | |||
124 | NEEDS ASSESSMENT SURVEY | Relocation Needs Assessment | 14301 - Appraisal Review (SS+60) | 12101 - NEGOTIATIONS 12901 - RELOCATION | A survey of the relocation needs for a project; Starts after appraisal work has begun / Finishes no later than the first delivery of reviewed and approved appraisal for negotiations (NEGOTIATIONS CANNOT BEGIN WITHOUT THE COMPLETED ASSESSMENT) |
125 | R/W DEMO & CLEAR WORK | 12901 - RELOCATION 27301 - FINAL R/W ORDER OF TAKING (FF) | 25501 - R/W CERTIFIED | As soon as right of way parcels are closed and FDOT has physical possession, any improvements on the property are cleared; Starts with possession of the first improved parcel / Finishes when the last parcel is clear and any last improvements are included in the plans | |
126 | UTILITY RELOCATION | | |||
127 | PH 42 ROW CONSULT CONTR EXECUT | | |||
128 | ASBESTOS SURVEY/ABATEMENT | | |||
129 | RELOCATION WORK | RELOCATION | 12401 - Relocation Needs Assessment | 12201 - CONDEMNATION (SS+130) 12501 - R/W DEMO & CLEAR WORK | This is time designated from time of purchase of first parcel until the moving completion of last homeowner impacted; Starts with the first delivery of relocation notices after an offer is made / Finishes when the last displacee inside the project�s limits of construction moves, regardless of whether a relocation claim is made |
130 | SOIL CROSS SECTION | | |||
131 | ROADWAY SOILS SURVEY | | |||
132 | ROADWAY SOILS REPORT | | |||
133 | FOUNDATION INVESTIGATIONS | | |||
134 | LANDSCAPE PLANS | | |||
135 | E.M.O. STUDY | | |||
136 | ARCHITECTURAL PLANS | | |||
137 | IN-HOUSE R/W LICENSE AGREEMNT | | |||
138 | R/W PRELIMINARY MAP | | |||
139 | FINAL R/W MAP | | |||
13901 | Prepare 60% RW Maps | 14201 - Submit Preliminary R/W Requirements 31506 - Review 90% Control Maps | 13902 - Submit 60% R/W Maps | The consultant prepares the 60% R/W maps in accordance with the District 2 R/W Map check list | |
13902 | Submit 60% RW Maps | 13901 - Prepare 60% R/W Maps | 11901 - R/W CONCEPT REVIEW MEETING 14001 - Review 60% R/W Maps | The consultant submits the 60% R/W maps to the Mapping section. The consultant does a thorough quality control check prior to submittal | |
13903 | Prepare 90% RW Maps | 14001 - Review 60% R/W Maps 32701 - FINAL R//W REQUIREMENTS RECEIVED BYSURVEY | 13904 - Submit 90% R/W Maps and Descriptions | The consultant prepares the 90% R/W maps and legal descriptions in accordance with the District 2 R/W Map check list | |
13904 | Submit 90% RW Maps | 11901 - R/W CONCEPT REVIEW MEETING (FF) 13903 - Prepare 90% R/W Maps | 14002 - Review 90% R/W Maps and Descriptions | The consultant does a thorough QC review and then submits the 90% maps and legal descriptions | |
13905 | Prepare 100% RW Maps | 14002 - Review 90% R/W Maps and Descriptions | 13906 - Submit 100% R/W Maps and Descriptions | The consultant finalizes the R/W maps and descriptions and address any title changes shown in the updated searches. | |
13906 | Submit 100% RW Maps | 13905 - Prepare 100% R/W Maps | 14004- Review 100% R/W Maps and descirptions | The consultant submits the 100% complete maps and descriptions to the Mapping section | |
140 | REVIEW CONSULTANT R/W MAP | | |||
14001 | Review 60% RW Maps | 13902 - Submit 60% R/W Maps | 13903 - Prepare 90% R/W Maps | The Mapping section reviews the 60% submittal against the District 2 check list, for errors and project specific information | |
14002 | Review 90% RW Maps | 13904 - Submit 90% R/W Maps and Descriptions | 13905 - Prepare 100% R/W Maps | The Mapping section will review the 90% submittal against the District 2 check list for errors and project specific information | |
14003 | Review 100% RW Maps | 13906 - Submit 100% R/W Maps and Descriptions | 14401 - Prepare Initial Parcel Packages | The Mapping section reviews the 100% submittal against the District 2 check list, errors and project specific information. | |
141 | CONCEPT STG RELOC PLAN | | |||
142 | SUBMIT PRE R/W REQUIREMENTS | 31507 - 100% R/W Control Maps Completed | 13901 - Prepare 60% R/W Maps 21001 - Review Preliminary R/W Requirements 14601 - Title Search Work | Using information from the Roadway Designer, the PM should submit the preliminary R/W requirements, based on his best information at the time. These requirements should be provided in graphic form, with the parcel lines being overlaid on a property appraisers aerial map. Exact parcel dimensions are not required at this time. | |
143 | APPRAISAL REVIEW | 12001 - APPRAISALS (SS+30) | 12401 - Relocation Needs Assessment (SS+60) | The time period for review of the real estate appraisals by FDOT Appraisal Review staff. The appraisals are approved for use in the negotiations to purchase required right-of-way for a project | |
14401 | INSTRUMENT PREP | Prepare Parcel Packages | 14004 - Review 100% R/W Maps and Descriptions | 26801 - SUBMIT 100% R/W MAPS AND PARCEL PACKAGES TO R/W | The Mapping Section will prepare the Parcel Information Sheets and assemble all parcel packages for the project |
14402 | Legal Instrument Preparation | 26801 - SUBMIT 100% R/W MAPS AND PARCEL PACKAGES TO R/W | 14403 - Revise/Update Parcel Packages (SS) 25501 - R/W CERTIFIED | This activity is used to account for any time used for preparing and/or updating additional legal instruments, parcel packages and/or R/W Maps after the initial documents have been submitted to R/W | |
14403 | Revise/Update Parcel Packages | 14402 - Legal Instrument Preparation (SS) | 25501 - R/W CERTIFIED | This activity is used to account for any time used for preparing and/or updating additional legal instruments, parcel packages and/or R/W Maps after the initial documents have been submitted to R/W | |
145 | PERMITS | | |||
146 | TITLE SEARCH WORK | 14201 - Submit Preliminary R/W Requirements | 14602 - Submit Title Search Package | The consultant Mapper orders the title work, begins reviewing the title and ownership documents for all affected properties, and provide the Department with copies of the title reports. This work should be performed in accordance with the R/W Manual, sections 4.1.3 and 4.1.6 | |
147 | GATHER STATISTICS | | |||
148 | M.O.T. PLANS | | |||
149 | UPDATE R/W MAPS AND INST. | | |||
150 | DIGITIZE TOPOGRAPHICS | | |||
151 | PREPARE FINAL R/W REQUIREMENTS | | |||
152 | PREPARE LIGHT. JUST. REP. | | |||
153 | PAVEMENT SURVEY | | |||
154 | PAVEMENT SURVEY REPORT | | |||
453 | R/W OTHER AGENCY ENCUMBER | Encumbrance Phase 48-LAP | | ||
454 | CONSTRUCT OTHR AGENCY ENCUMBER | Encumbrance Phase 58-LAP | | ||
155 | UPDATE SCOPE OF WORK | 25001 - Begin Work | 23201 - Design Consultant Acquisition | Review intent of work; perform scoping plans and review of all changes, estimate, survey request and any additional work that needs to be included in the scope | |
156 | CAT. EX. APPROVED | | |||
157 | R/W MAP COMPLETE | | |||
158 | PRE-BID CONFERENCE | | |||
159 | COLOR CODE UTILITY PLANS | | |||
160 | INTERCHANGE JUSTIFY REPORT | | |||
161 | INTERCHANGE MODIFY REPORT | | |||
162 | INTERCHANGE REPORTS | FHWA Determination letter | | ||
163 | MAINT OR FUNDS AGREEMENT | | |||
1630000 | IDENTIFY MA NEED | 11302 - Prepare PH II Plans | 16300 - MA DOCUMENTATION RECEIVED | The Project Manager determines the need for a Maintenance Agreement; determination includes work involved with a state, county, city or local facility | |
1630050 | MA DOCUMENTATION RECEIVED | 16300 - IDENTIFY MA NEED | 16300 - PROCESS MAINTENANCE AGREEMENT 90201 - SUBMIT PH II PLANS (FS-11) | ||
1630010 | PROCESS MA AGREEMENT | | |||
1630100 | NO MA REQUIRED | 16300 - IDENTIFY MA NEED | 20401 - PRODUCTION DATE | ||
1630200 | MA EXECUTION | 16300 - PROCESS MAINTENANCE AGREEMENT | 20401 - PRODUCTION DATE | ||
164 | PREPARE SCOPE OF WORK | 3R REPORT | | ||
165 | TRAFFIC SIGNAL STUDY | | |||
166 | ALTERNATIVE CONTRACT PAYMENT | | |||
167 | SIGNAL SYSTEM ANALYSIS | | |||
168 | Q. A. REVIEW | | |||
169 | PRELIM. FIELD REVIEW | | |||
170 | R/W CONTROL SURVEY | | |||
171 | REQUEST CONTRACT TIME (for DB) | CONTRACT TIME MEMO (Conventional) | 90301 - SUBMIT PH III PLANS | 20401 - PRODUCTION DATE | The period of time, measured in calendar days, allowed for completion of the construction contract to include all holidays and special events |
172 | CHECK LIST ACTIVITIES | | |||
1720581 | CHECK LIST ACTIVITIES | SUBMIT FINAL SIGNED CHECKLIST (LA) 525-010-44) | | ||
1720582 | SUBMIT FINAL CHECKLIST TO C.O. | | |||
173 | RAILROAD ACTIVITIES | | |||
174 | CONTAMINATION TESTING | | |||
175 | RESEARCH STUDIES | | |||
176 | MINORITY BUSINESS ENTERPR. REV | | |||
178 | CENT. OFFICE PROCESS PLANS PKG | | |||
179 | PH A8 ADMIN OTHER AGNCY ENCUMB | | |||
180 | FILE PROJECT RESOLUTION | | |||
181 | DESIGN BUILD R/W CERTIFICATION | | |||
182 | REQUEST BRIDGE NUMBER | | |||
183 | BEGIN BRDGE LOAD RATING | | |||
184 | SUBMIT BRDGE LOAD RATING | | |||
185 | REVIEW BRDGE LOAD RATING | | |||
186 | APPROVE BRDGE LOAD RATING | | |||
187 | NO R/W REQRD CERTIFICATION | 22201 - ALL PERMITS CLEAR 90402-Submit Final Plans | 38001 - PRODUCTION READY | A date that represents that there are no R/W certifications required | |
18800 | PRELIMINARY REVIEW | Preliminary Engineering Certification (PEC) | 90401 - SUBMIT PH IV PLANS | 20401 - PRODUCTION DATE | |
18801 | DRAFT RFP REVIEW | | |||
18805 | REVIEW R/W DOCUMENTS FROM LA (FDOT) | | |||
189 | FINAL REVIEW | | |||
18901 | FINAL RFP REVIEW | | |||
190 | PERMIT EXPIRATION | | |||
191 | TEMP. CONST. EASEMENT EXPIRATN | | |||
192 | UPDATE ETDM PROGRAMMING | | |||
193 | Local Funds Deposited w Comptroller | | |||
194 | CONSTRUCTION MATERIAL PURCHASE | PUSHBUTTON (MULTI-YEAR FUNDS) - 280 used for the Actual Let | | ||
194280 | Multi-Year - Lettings | | |||
195 | AVAILABILITY PAYMENT | | |||
196 | FINAL ACCEPTANCE PAYMENT | | |||
197 | PAVEMENT DESIGN | | |||
198 | PAVEMENT SURVEY VALIDATION | | |||
19900 | PLANS SUBMIT TO DIST ESTIMATES | REVIEW LRE UNIT PRICES (any unit price review) | | ||
199164 | REVIEW LRE UNIT PRICES (3R Report) | | |||
200 | PROJECT ADVERTISEMENT | Planned Advertisement | | ||
52200 | Central Office Approval for Planned Advertisement | | |||
204 | PRODUCTION DATE | 16302 - MA EXECUTION 44502 - MA/RW TRANSFER AGREEMENT EXECUTION 37601 - ENVIRONMENTAL CERTIFICATION 26601 - UTILITIES CERTIFIED 25501 - R/W CERTIFIED 22201 - ALL PERMITS CLEAR 19908 - Review Trnsport Unit Prices - PH IV 18800 - Preliminary Engineering Certification 17101 - Contract Time Memo 38001 - PRODUCTION READY | 22601 - PS&E SUBMITTAL(S) (60 Day Ad) | The date committed for the completion of the project and marks the date that the project (Plans, Specs & Estimates Package) will be transmitted (mailed) to Tallahassee or District Contracts. | |
205 | CNST UTILITY CONTRACT EXECUTED | | |||
206 | STATE FIRE MARSHALL | | |||
207 | TITLE SEARCH CONTRACT | | |||
208 | APPRAISAL CONTRACT | 34901 - PH. 4B Encumbered | 12001 - APPRAISALS | The time period which allows the FDOT to hire a consultant fee appraiser to perform appraisal services. During this period the FDOT Appraisal Administrators review the project, discuss a general scope of services and determine appropriate contracting services. The appraisal services are then advertised or contracted with a districtwide contract; Starts when the Appraisal Contracts administrator engages the fee appraiser / Finishes when the last LOA is issued on initial appraisal | |
209 | R/W OCCUPANCY PERMIT | | |||
210 | REVIEW PRELIM R/W REQUIREMENTS | 14201 - Submit Preliminary R/W Requirements | 14603 - Review Title Search Package | The Mapping section along with representatives from R/W and Design will review the preliminary R/W requirements and make suggestions on how to reduce costs and impacts | |
211 | CONSULT. CONTRACT COMPLETE | | |||
212 | TRANSMIT PKG FOR LETTING | 24203 - PS&E Submittal Review(s)(FS+5) | 28001 - LETTING DATE (FS+51) | ||
213 | LOCAL PERMIT | | |||
214 | DER/WATER/SEWER PERMIT | | |||
215 | DER DF/SW PERMIT | | |||
216 | DNR PERMIT | PROCESSING COASTAL CONSTRUCTION (STATE) PERMIT | | ||
217 | USCE PERMIT | PROCESSING SECTION 404 (FEDERAL) PERMIT | 27201 - SUBMIT PERMIT APPLICATIONS | 22201 - ALL PERMITS CLEAR 38001 - PRODUCTION READY | |
218 | USCG PERMIT | PROCESSING USCG (FEDERAL) PERMIT | | ||
219 | WATER MNGMT DIST PERMITS | PROCESSING ERP (STATE) PERMIT | 27201 - SUBMIT PERMIT APPLICATIONS | 22201 - ALL PERMITS CLEAR 38001 - PRODUCTION READY | |
220 | UPDATE PLANS | | |||
221 | ACCESS MANAGEMENT REVIEW | | |||
22201 | ALL PERMITS CLEAR | ALL PERMITS CLEAR | 21702 - SECTION 404 PERMIT PROCESSING (Federal) 21902 - ERP PERMIT PROCESSING (State) | 20401 - PRODUCTION DATE | All Permits necessary for construction of the project have been obtained. These permits include but are not limited to water management district permits, ACOE, Coast Guard, NPDES, local government, etc. |
22202 | NO PERMIT REQUIRED | | |||
22209 | PERMIT for DesignBuild for Advertisment | | |||
223 | MAJ/NON-MAJ STATEMENT | FINAL ENVIRONMENTAL DOCUMENTS | | ||
224 | ADVANCE NOTIFICATION | | |||
225 | FHWA CONCUR M/NM STATEMENT | | |||
226 | PLANS TO DIST SPECS | | |||
227 | FINAL R/W MAP APPROVAL | | |||
228 | SUBMIT UTILITY DATA | | |||
229 | ADVERTISE DISTRICT CONTRACT | | |||
230 | CONSULTANT SCOPE MEETING | | |||
231 | SUBMIT CONSULTANT PACKAGE | | |||
232 | DESIGN CONSULTANT ADVERTISE | 15501 - Update Scope of Work 25001 - Begin Work | 23301 - PH 32 CONTRACT EXECUTED (C-XXXX) | ||
233 | P.E. CONTRACT EXECUTED | 23201 - Design Consultant Acquisition | 23432 - Design NTP | Also labeled NTP (Notice to Proceed), this is the date that the contract between the Department and the Consultant is officially executed; This is the first day that the consultant is billable. | |
234 | NOTICE TO PROCEED | 23301 - PH 32 CONTRACT EXECUTED (C-XXXX) | 25401 - Design Survey Requested | Once a contract is executed, a Notice-to-Proceed letter is issued to the consultant identifying the date work can begin. This date must be on or after the date of execution of the contract | |
23401 | NOTICE TO PROCEED (PLANNING) | | |||
23402 | NOTICE TO PROCEED (PD&E) | | |||
23403 | NOTICE TO PROCEED (DESIGN) | | |||
23404 | NOTICE TO PROCEED (R/W) | | |||
234052 | NOTICE TO PROCEED (CST 1,7,9) | | |||
234058 | NOTICE TO PROCEED (CST 5-LAP) | | |||
23406 | NOTICE TO PROCEED (CEI) | | |||
235 | SUBMIT PLANS FOR REVIEW | | |||
236 | FINAL EVALUATION OF CONSULT | | |||
237 | FHWA AUTHORITY RECEIVED | | |||
238 | INTERIM EVALUATION OF CONSULT | | |||
239 | P.D.& E CONTRACT EXECUTED | | |||
240 | COMPILE SUIT DATA | | |||
241 | SAFETY RECOMMENDATIONS | | |||
242 | SPECIFICATIONS | | |||
24201 | Division I Specifications for Design Build | | |||
24202 | VOLUME II DATA RELEASE | | |||
243 | ALL R/W CLEARED | APP R/W CERTIFICATION | | ||
244 | IDENTIFY PROPERTY OWNER | | |||
245 | FINAL BID ABILITY | FINAL BIDABILITY REVIEW | 90301 - SUBMIT PH III PLANS | 30301 - Review PH III Plans (SS) | Review of Pay Items and Quantities using the plans and CADD.zip file to make sure pay item are not missing and all the quantities are included |
246 | FINAL ENGINEERING REPORT | | |||
247 | LOCAL GOVERNMENT AGREEMENT | LOCAL AGENCY RESOLUTION | | ||
248 | D.M.S APPROVAL | | |||
249 | TECHNICAL PROPOSAL DUE | TECHNICAL PROPOSAL due Date in District Office | | ||
250 | P.E. BEGIN | Begin Work | 15501 - Update Scope of Work 30401 - Pavement Data Requested 25401 - Design Survey Requested 23201 - Design Consultant Acquisition | This item signifies the start of the project's design. Project begins and Phase 31 is authorized | |
251 | FUND AGREEMENTS TO TALLAHASSEE | LFA Sent/Received | | ||
25101 | No LFA Required | | |||
25102 | | ||||
252 | PROGRAM PROJ W/FHWA | | |||
253 | PLANNING CONTRACT EXECUTED | | |||
254 | ORDER AERIALS | | |||
25401 | Design Survey Wk Requested | 23432 - Design NTP 25001 - Begin Work | 10601 - Design Survey Work | Send survey request of intended work to District Land Surveyor typically two years before the job officially begins | |
255 | R/W CERTIFIED | 12201 - CONDEMNATION 14403 - Revise/Update Parcel Packages (FF) 14402 - Legal Instrument Preparation 12501 - R/W DEMO & CLEAR WORK (FF) | 20401 - PRODUCTION DATE | The project is certified clear for construction when FDOT has title to all the right-of-way, relocation is complete and all improvements have been cleared; Starts and Finishes the same day and not before R/W Demo and clear finishes | |
256 | ORDER DESIGN TRAFFIC | | |||
257 | DESIGN TRAFFIC RECEIVED | | |||
258 | SUBMIT DRAFT ENV DOCUMENTS | | |||
259 | ENV DRAFT CIRCULATION | | |||
260 | TYPICAL SECTION APPROVED | | |||
262 | CONDUCT PUBLIC HEARING | PD&E PUBLIC HEARING | | ||
263 | LOC/DES APPROVAL | NEPA APPROVAL | | ||
264 | UTILITY CONTACT | | |||
265 | UTILITY PRE-DESIGN CONF | | |||
266 | NEPA COA UNKNOWN | | |||
267 | RAILROAD CONTACT | | |||
268 | DOCUMENTS TO R/W | 14401 - Prepare Initial Parcel Packages 14603 - Review Title Search Package | 14402 - Legal Instrument Preparation 34901 - PH. 4B Encumbered | The Mapping section delivers completed R/W maps and parcel packages to the R/W section and updates this activity in the PSM schedule accordingly | |
269 | ALL UTILITIES CLEAR | | |||
270 | SUBMIT BRIDGE PACKAGE | | |||
271 | GEOTECH EVALUATION | 10801 - Final Design Survey Approved | 27102 - Geotech Work | Geotechnical work involves services for soil borings and/or investigation for new road construction, widening of roadways and shoulders, turn lanes, and ponds for miscellaneous structures and bridge foundations | |
272 | FILE PERMITS | SUBMIT PERMIT APPLICATION | 90201 - SUBMIT PH II PLANS | 21702 - SECTION 404 PERMIT PROCESSING (Federal) 21902 - ERP PERMIT PROCESSING (State) | All permit applications are submitted to various permitting agencies by the District Permits Administrator |
273 | FINAL R/W ORDER OF TAKING | 12101 - NEGOTIATIONS | 12501 - R/W DEMO & CLEAR WORK (FF) | The date by which the final order of taking must take place in order for the project to be cleared by the scheduled Right-of-Way Certification date; Starts when the last Order of taking in entered / Finishes when the last Date of Deposit is made | |
274 | SUBMIT BHR | | |||
275 | STUDY COMPLETE | | |||
276 | ENV DRAFT PREPARATION | | |||
277 | SUBMIT BDR | | |||
278 | ADVERTISMENT FOR LETTING | CONSTRUCTION ADVERTISEMENT (conventional) | | ||
279 | RAILROAD CLEAR | | |||
280 | LETTING DATE | 21201 - Transmit PS&E Package (FS+51) | 20301 - PH.62 CEI Add/Suppl. (C-XXXX) Seq.1 31201 - CONSTRUCTION (FS+43) 20302 - PH.62 CEI Add/Suppl. (C-XXXX) Seq.21 | The date that the Department opens the bid proposals from Contractors | |
281 | SUBMIT RR DATA | 21201 - Transmit PS&E Package | 38001 - PRODUCTION READY | ||
282 | R/W UTILITY CONTRACT EXECUTED | | |||
283 | OPEN DESIGN BUILD BID | OPEN DESIGN BUILD BID (Price Proposal) | | ||
284 | EXECUTE DESIGN BUILD | EXECUTE DESIGN BUILD CONTRACT | | ||
285 | RFP/DES BUILD PKG APPROVAL | RFP/Design Package Approval | | ||
286 | FINAL ENV DOC TO FHWA | | |||
287 | FHWA REVIEW FIN ENV DOC | | |||
288 | TREE MITIGATION (D2) | | |||
289 | LAP LETTING | | |||
290 | COMMUNITY AWARE PLAN COMPLETE | | |||
291 | THERMO QUANTITIES TO PM | | |||
292 | PUBLIC INFO MEETING | PD&E PUBLIC INFO MEETING | | ||
293 | ADVERT. PUBLIC HEARING | | |||
294 | PROCESS EXCEPTIONS/VARIANCE | | |||
295 | PREPARE ENVIRONMENT. DOC. | | |||
296 | ENV. IMPACT STATEMNT APPROVED | | |||
297 | CONST. ESTIMATE UPDATE | | |||
298 | R/W ESTIMATE UPDATE | | |||
299 | REQUEST FOR AUTHORIZATION | | |||
300 | RIGHT OF WAY SURVEY | | |||
301 | PHASE I PLANS REVIEW | 90101 - SUBMIT PH I PLANS | 19902 - Review LRE Unit Price - PH I (FF) | The review of PH I/PH II Plans consist of reviewing the design elements using the PPM to ensure standards and criteria are met; review plans to ensure that proposed construction can be performed within R/W shown; Review plans to ensure that all major elements needed for intended construction are included; review plans using PPM guidance to ensure plan assembly are correct; review plans using checklist to ensure components are complete | |
302 | PHASE II PLANS REVIEW | 90201-Submit PH II Plans 90701 - CONSTRUCTABILITY REVIEW (FF) | 19904 - Review LRE Unit Price - PH II (FF) 11303-Prepre PH III Plans | The PH II Plan review includes but is not limited to ensuring that design elements using PPM meet standards and criteria, ensures that the proposed construction can be performed within the R/W shown, ensures that all major elements needed for intended construction are included, ensures that the PPM guidance is used as a standard guaranteeing that plan assembly is correct | |
455 | C.E.I. OTHER AGENCY ENCUMBER | Encumbrance Phase 68-LAP | | ||
456 | MAINT. OTHER AGENCY ENCUMBER | Encumbrance Phase 78-LAP | | ||
457 | OPERATNS OTHER AGENCY ENCUMBER | Encumbrance Phase 88-LAP | | ||
458 | ADVERTISE DESIGN BUILD | | |||
459 | LETTERS OF INTEREST | | |||
460 | RFP TO FHWA FOR REVEIW | | |||
461 | FHWA RFP APPROVAL | | |||
303 | PHASE III PLANS REVIEW | 24501 - FINAL BIDABILITY REVIEW (SS) 90301 - SUBMIT PH III PLANS | 11304 - Prepare PH IV Plans - (100%) 19906 - Review Trnsport Unit Prices - PH III (FF) | The review of PH III Plans consist of reviewing the design elements using the PPM to ensure standards and criteria are met; review plans using PPM guidance to ensure plan assembly are correct; review plans using checklist to ensure components are complete; review plans, quantities, and pay items to ensure plans completion and accuracy | |
304 | CORING | 30401-Pavement Data Requested/30402-Pavement Data Received | 25001 - Begin Work | 30402 - Pavement Data Received | The Pavement Section in the Materials and Research Office will provide necessary corings for the roadway and will provide the report with milling and resurfacing recommendations to the FDOT Project Manager. The EOR and FDOT PM initiate coordination and should work closely with the Materials office to set the areas to be cored and analyzed early in the process. |
305 | PLANS TO FINAL PROCESSING | | |||
306 | P.S.& E MEETING | | |||
307 | STRUCT. REVIEW (PRELIM) | | |||
308 | STRUCT. REVIEW (FINAL) | | |||
309 | WORK PROGRAM AMENDMENT | | |||
31001 | PHASE IV PLANS REVIEW | REVIEW PH IV/FINAL BIDABILITY BK CK | 90401 - SUBMIT PH IV PLANS | 31004 - Address PH IV Comments | |
31004 | Address PH IV Comments | 31001 - Review PH IV Plans / Bidability Backcheck | 38001 - PRODUCTION READY | ||
311 | STRUCT. REVIEW (BDR) | | |||
312 | CONSTRUCTION | 20301 - PH.62 CEI Add/Suppl. (C-XXXX) Seq.1 28001 - LETTING DATE (FS+43) 20302 - PH.62 CEI Add/Suppl. (C-XXXX) Seq.21 | | Allotted time per the Contract Time Memo that it will take for Construction to be completed | |
313 | TEST RESULTS RECEIVED | | |||
314 | THERMO/PAVEMENT MARKING PLANS | | |||
315 | R/W CONTROL MAP | | |||
31501 | Prepare 60% Control Maps | 106-Design Survey Work | 31502-Submit 60% Control Maps | Maps representative of the baseline and centerline of survey, baseline alignment detail sheets and preliminary survey data reflecting the graphical project layout | |
31502 | Submit 60% Control Maps | 31501-Prepare 60% Control Maps | 31503-Review 60% Control Maps | The 60% control map includes all items described in the District 2 Control Map check list, including but not limited to: project alignment; reference points including project network control points, section corners, quarter section corners, center of section corners and fractional corners, where applicable; subdivision boundaries, condominium boundaries and all public right-of-way lines. | |
31503 | Review 60% Control Maps | 31502-Submit 60% Control Maps | 31504-Prepare 90% Control Maps | The Mapping section reviews the submitted map against the District 2 check list for errors identified and to ensure that project specific information is corrected | |
31504 | Prepare 90% Control Maps | 31503-Review 60% Control Maps | 31505-Submit 90% Control Maps | Maps representative of the signed and sealed survey and the graphical project layout including section lines and the coordinate geometry alignment; this mapping data becomes the foundation and basis of the R/W map development phase | |
31505 | Submit 90% Control Maps | 31504-Prepare 90% Control Maps | 31506-Review 90% Control Maps | The 90% control map should include all items described in the District 2 Control Map check list: All electronic field books, including databases and surveyors reports; should be finalized and all certified corner records processed | |
31506 | Review 90% Control Maps | 31505-Submit 90% Control Maps | 31507-100% RW Control Maps Completed 13901 - Prepare 60% R/W Maps | The Mapping section will review the submitted map against the District 2 check list for errors and project specific information | |
31507 | 100% RW Control Maps Completed | 31506-Review 90% Control Maps | 14201-Submit Preliminary RW Requirments | The 100% control map, certified by a Professional Surveyor and Mapper, is submitted to the Department where it is reviewed and accepted by the Mapping section. All comments from previous reviews have been addressed. The consultant submits signed and sealed mylars and prints. | |
316 | CONSTRUCT THERMO/PVMT MARKING | | |||
317 | OPER CONSULT CONTRACT EXEC | | |||
318 | CAP CONSULT CONTRACT EXEC | | |||
319 | SUBMIT FINAL R/W REQUIREMENTS | | |||
320 | REVIEW FINAL R/W REQUIREMENTS | | |||
321 | R/W TITLE SEARCH REQ. | | |||
322 | R/W REQUIRE. TO R/W ENG. | | |||
323 | RETENTION/MITIGAT R/W REQRMTS | | |||
324 | MAINT MAPS PREP AND PROCESS | | |||
32501 | TIITF & OTHER GOV DOC | Identify TIITF Need with Survey and Mapping office | AE155 (Finalize Scope or AE250 (Begin Work) | AE 233 Contract Execution or AE 11301 AE 11501 | Placeholder activity used when a TIITF parcel is needed on a project but can�t be submitted to DEP until other requirements have been met |
32502 | TIITF & OTHER GOV DOC | Processing TIITF | | ||
326 | PARCEL IDENTIFICATION | | |||
327 | DETAIL PARCEL REVIEW | FINAL R/W REQUIREMENTS RECEIVED BY SURVEY | 90201-Submit PH II Plans | 13903 - Prepare 90% R/W Maps | |
328 | FCC CERTIFICATION REQUIRED Y/N | | |||
329 | ENVIRONMENTAL REVIEW | | |||
330 | CEI BEGIN | | |||
331 | SPEC ENG/ENV STUDIES | DRAFT ENVIRONMENTAL DOCUMENTS COMPLETE | | ||
332 | EARLY NOTIFICATION PROCESS | | |||
333 | CULTURAL RESOURCES ASSESS SURV | | |||
335 | PD&E NOISE STUDY COMPLETE | | |||
336 | ENVIRONMENTAL REEVALUATION | | |||
338 | ASSESS RISK INVOLVEMENT | ASSESS RISK INVOLVEMENT (CSRA Workshop) | | ||
33801 | PERFORM COST RISK ANALYSIS | | |||
339 | VALUE ENGINEERING REVIEW | | |||
340 | ADV ACQUISITION PARCEL DOCS | | |||
341 | ASSEMBLE ADV ACQ PARCEL PCKG | | |||
342 | ADVANCED ACQUISITION APPRAISAL | | |||
343 | ADV ACQUISITN APPRAIS REVIEW | | |||
344 | ADVANCE ACQUISITN NEGOTIATION | | |||
345 | ADV ACQUISTN DEMO & CLEAR | | |||
346 | ADV ACQ R/W CONSULT CONTRACT | | |||
347 | ADVANCE ACQUISITION RELOCATION | | |||
348 | PARTNERSHIP MEETING | If no meeting change to "No Pass the Torch Meeting" | | ||
34801 | PASS THE TORCH MEETING DATE | | |||
349 | PH 4B ROW SERVCE CONTRACT EXEC | 26801 - SUBMIT 100% R/W MAPS AND PARCEL PACKAGES TO R/W | 20801 - Appraisal Contract | Activity placed in schedule to represent when funding for specific phase is encumbered | |
350 | MAINTENANCE CONTRACT EXECUTED | | |||
351 | AUTHORIZE RW PURCHASE | | |||
352 | AUTHORIZE RW RELOCATION | | |||
353 | TYPE 1 CATEGORICAL EXCLUSION | | |||
354 | PCE (PROGRAM CATEG EXCLUSION) | | |||
355 | NMSA (NON MAJOR STATE ACTION) | | |||
356 | EIS (ENVIRON IMPACT STATEMENT) | | |||
357 | TYPE 2 CE (CATEG EXCLUSION) | | |||
358 | EA/FONSI (ENVIRON ASSESMENT) | | |||
359 | COMMUNITY INVOLVEMENT | | |||
360 | SEIR (STATE ENV IMPACT REPORT) | | |||
361 | R/W MAPS TO FHWA | | |||
362 | R/W MAPS APPROVED | | |||
363 | DATA COLLECTION | | |||
364 | ALTERNATIVE DEVELOPMENT | | |||
365 | PREPARE FOR PUBLIC MEETING | | |||
366 | PREPARE FOR PUBLIC HEARING | | |||
367 | DEVELOP PREFERRED ALIGNMENT | | |||
368 | ENV/ROW ANALYSIS | | |||
369 | FINALIZE PE REPORT | | |||
370 | PLANS TO DIST CONTRACT | | |||
371 | SUBMIT PAVE TYPE RPT INITIAL | | |||
372 | SUBMIT PAVE TYPE RPT 30% (PH1) | | |||
373 | SUBMIT PAVE TYPE RPT 60% (PH2) | | |||
380 | PRODUCTION READY PLANS | 12201 - CONDEMNATION 31004 - Address PH IV Comments 28101 - NO RAIL INVOLVEMENT 26411 - Utility Coordination II 21902 - ERP PERMIT PROCESSING (State) 21702 - SECTION 404 PERMIT PROCESSING (Federal) | 20401 - PRODUCTION DATE | The district production complete date (A/E 204, in PSM) plus two months. This allows one month for plans review and submittal and one month for central office processing, at which time a project is ready for FHWA�s authorization and/or the OOC�s approval of funds/budget and advertisement for receipt of bids | |
381 | PREPARE PHI (30%) DESIGN PLN | | |||
382 | PREPARE PHII (60%) DESIGN PLN | | |||
383 | PREPARE PHIII (90%) DESIGN PLN | | |||
384 | PREPARE PHIV (100%) DESIGN PLN | | |||
385 | PREPARE PHI (30%) BRIDGE PLN | | |||
386 | PREPARE PHII (60%) BRIDGE PLN | | |||
387 | PREPARE PHIII (90%) BRIDGE PLN | | |||
388 | PREPARE PHIV (100%) BRIDGE PLN | | |||
389 | REVIEW PHI (30%) BRIDGE PLN | | |||
390 | REVIEW PHII (60%) BRIDGE PLN | | |||
391 | REVIEW PHIII (90%) BRIDGE PLN | | |||
392 | REVIEW PHIV (100%) BRIDGE PLN | | |||
400 | CEI CONSULT. ACTIVITIES | | |||
401 | CONSULT SHORTLISTING | | |||
402 | CONSULT FINAL SELECTION | | |||
40201 | Public Meeting of Selection Committee to review and confirm Letter of Interest scores - ASDB | | |||
40202 | Public Meeting Date of Selection Committee to determine intended Award - LBDB and ASDB | | |||
403 | CEI SCOPE OF WORK | | |||
404 | CEI SUBMIT CONSULT PKGE | | |||
405 | CEI CONSULTANT ADVERTISE | | |||
406 | CEI CONSULT SHORTLISTING | | |||
407 | CEI CONSULT FINAL SELECTION | | |||
408 | CEI ENCUMBERED | | |||
417 | AUTHORIZE R/W IN-HOUSE | PHASE 41 FUNDING (Use for 41 when Docs not delivered to RW) | | ||
418 | R/W ENG SCOPE OF WORK | | |||
419 | R/W ENG SUBMIT CONSULT PKGE | | |||
420 | R/W ENG CONSULT ADVERTISE | | |||
421 | R/W ENG CONTR EXECUTED | | |||
422 | R/W ENG CONSULT SHORTLIST | | |||
423 | R/W ENG CONSULT FINAL SELECT | | |||
424 | R/W SCOPE OF WORK | | |||
425 | R/W SUBMIT CONSULT PKGE | | |||
426 | R/W CONSULT ADVERTISE | | |||
427 | R/W CONSULT SHORTLIST | | |||
428 | R/W CONSULT FINAL SELECTION | | |||
445 | OWNERSHIP AGREEMENT | | |||
4450100 | IDENTIFY RW TRANSER NEED | 11302 - Prepare PH II Plans | 44501 - PROCESS MA/RW TRANSFER AGREEMENT 44505 - R/W TRANSFER AGREEMENT DOCUMENTATION RECEIVED | A review of the R/W requirements to determine if any off system or county property is needed to construct a project; once identified and property acquired by DOT, an agreement is reached transferring the property to the Local Agency for maintenace purposes | |
4450200 | NO RW TRANSFER AGREEMENT REQUIRED | 44501 - IDENTIFY R/W TRANSFER NEED | 20401 - PRODUCTION DATE | ||
4450300 | RW TRANSFER AGREEMENT DOCUMENTATION RECEIVED | | |||
4450400 | PROCESS MA/RW AGREEMENT | 44501 - IDENTIFY R/W TRANSFER NEED 44505 - R/W TRANSFER AGREEMENT DOCUMENTATION RECEIVED | 44502 - MA/RW TRANSFER AGREEMENT EXECUTION | ||
4450500 | MA/RW TRANSFER AGREEMENT EXECUTION | 44501 - PROCESS MA/RW TRANSFER AGREEMENT | 44501 - PROCESS MA/RW TRANSFER AGREEMENT 90201-SUBMIT PH II PLANS (FS-11) | ||
447 | Federal Authorization of LAP project | | |||
448 | PLANNING OTHER AGENCY | Encumbrance Phase 18-LAP | | ||
449 | LAP PH 28 PD&E AUTHORIZATION | | |||
450 | TIP / STIP AMENDMENT | | |||
451 | P.D.& E OTHER AGENCY ENCUMBER | Encumbrance Phase 28 -LAP | | ||
452 | P.E. OTHER AGENCY ENCUMBER | Encumbrance Phase 38-LAP | | ||
46101 | FHWA RFP APPROVAL to Ad - LBDB, ASDB | | |||
46102 | FHWA Concurrence to Award - LBDB, ASDB | | |||
46200000 | SHORT LIST | Shortlist Posting Date | | ||
46201000 | OPTIONAL PRE PROPOSAL MEETING - LBDB | | |||
46202000 | MANDATORY (optional) PRE PROPOSAL MEETING - ASDB | | |||
46256000 | Utility Pre_Proposal Meeting | | |||
463 | P.E. CONSULTANT FINAL SELECTN | | |||
464 | ORAL PRESENTATIONS | | |||
470 | TRC MEETING - Submit LOI Scores, | | |||
471 | RELEASE OF FINAL RFP to Shortlisted Firms | | |||
47201 | ATC MEETING 1 | | |||
47202 | ATC MEETING 2 | | |||
47203 | ATC MEETING 3 | | |||
473 | PAGE TURN MEETING | | |||
474 | | ||||
47401 | Q & A Deadline for DB Firm to Submit Questions-LBDB | | |||
47402 | FDOT Deadline to submit Responses - LBDB | | |||
47403 | QUESTION AND ANSWER MEETING (Optional) -LBDB | | |||
475 | | ||||
47501 | Deadline for Design-Build Firms to submit ATC Proposals and for the submission of Design Exceptions or Variations | | |||
47502 | Deadline for Department Responses to ATC Proposals | | |||
476 | | ||||
47601 | Addendum issued for approved Design Exceptions | | |||
47602 | Deadline for submittal of ATC Proposals for which the Dept requested addt'l info & were not approved or new ATCs that are a direct response to an Addendum issued | | |||
477 | DDE completes review of ATCs and notifies Design-Build Firms | | |||
478 | | ||||
47801 | Deadline for Questions prior to Technical Proposal to the Pre-Bid Q&A website | | |||
47802 | Deadline for FDOT Response prior to Technical Proposal to the Pre-Bid Q&A website | | |||
47803 | Q&A from FDOT to Firm - Written Response | | |||
47804 | Q&A response from Firm - Written Response | | |||
479 | Deadline for Department to post responses to Pre-Bid Q&A website | | |||
480 | Deadline for the Design Build Firm to submit a written statement per SectionIII, Threshold Requirements | | |||
501 | APP APPROVE BY DATE FOR PLAN | | |||
502 | APP APPROVE BY DATE FOR PD&E | | |||
503 | APP APPROVE BY DATE FOR PE | | |||
504 | APP APPROVE BY DATE FOR ROW | | |||
505 | APP APPROVE BY DATE FOR CONST | | |||
508 | APP APPROVE BY DATE FOR OP/GR | | |||
509 | APP APPROVE BY DATE FOR CAP/GR | | |||
600 | APP REPORT COMMENTS | | |||
601 | APP ADVANCE DATE FOR PLAN | | |||
602 | APP ADVANCE DATE FOR PD&E | | |||
603 | APP ADVANCE DATE FOR PE | | |||
604 | APP ADVANCE DATE FOR ROW | | |||
605 | APP ADVANCE DATE FOR CONST | | |||
608 | APP ADVANCE DATE FOR OP/GR | | |||
609 | APP ADVANCE DATE FOR CAP/GR | | |||
700 | ETDM/ETAT PROG. SCREEN START | | |||
701 | ETDM PROG PRELIM SUM REP PUB | | |||
702 | ETDM PROG FINAL SUM REP PUB | | |||
703 | PD&E SCOPE AND SCHEDULE COMPL | | |||
704 | ASSIGN PD&E PROJECT MANAGER | | |||
705 | PD&E ADVERTISEMENT | | |||
706 | TYPE 2 CE START | | |||
707 | EA START | | |||
708 | NOI - EIS START | | |||
709 | SEIR START | | |||
710 | PLANNING CONSISTENCY COMPL | | |||
711 | ALTERNATIVES WORKSHOP | | |||
712 | ALTERNATIVES DEVELOPMENT COMPL | | |||
713 | DISTRICT QC OF DRAFT ENV DOC | | |||
714 | DEIS TO SEMO OEM | | |||
715 | DEIS SEMO APPROVAL | | |||
716 | DEIS TO FHWA | | |||
717 | DEIS FHWA APPROVAL | | |||
718 | EA TO SEMO | | |||
719 | EA APPROVED SEMO | | |||
720 | EA TO FHWA | | |||
721 | EA APPROVED FHWA | | |||
722 | TYPE 2 TO FHWA | | |||
723 | OEM - NOI REVIEW | | |||
724 | FEIS TO SEMO | | |||
725 | FEIS SEMO APPROVED | | |||
726 | FEIS TO FHWA | | |||
727 | FEIS FHWA APPROVED | | |||
728 | FEIS/ROD TO SEMO APPROVED | | |||
729 | FEIS/ROD TO FHWA APPROVED | | |||
730 | ROD TO SEMO APPROVED | | |||
731 | ROD TO FHWA APPROVED | | |||
732 | FONSI TO SEMO APPROVED | | |||
733 | FONSI TO FHWA APPROVED | | |||
734 | SEIR APPROVED | | |||
735 | CO-LEGAL SUFFICIENCY REVIEW | | |||
736 | LDCA PUBLIC NOTICE | | |||
737 | ENV DOC REEVALUATIONS - PE | | |||
738 | FEDERAL REGISTER NOTICE | | |||
739 | ENV DOC REEVALUATIONS - R/W | | |||
740 | NEPA COA UNKNOWN | | |||
741 | ENV DOC REEVAL - DESIGN CHANGE | | |||
742 | EA COA CHANGE | | |||
743 | ON HOLD | | |||
744 | FEDERAL / STATE CHANGE | | |||
745 | OFF HOLD | | |||
746 | SWAT PLANNING MEETING | | |||
747 | SWAT KICK-OFF MEETING | | |||
748 | ENV DOC REEVAL-CONST ADVERTSMT | | |||
749 | TYPE 1 CE APPROVAL | | |||
750 | WETLAND REPORT | | |||
751 | SECTION 4(F) | | |||
752 | INFORMAL USFWS CONSLT COMP | | |||
753 | FORMAL USFWS CONSULT COMP | | |||
756 | SECTION 106 EFFECTS/ 267 F.S. | | |||
757 | TRAFFIC ANALYSIS/REPORT | | |||
758 | CORRIDOR ANALYSIS | | |||
759 | TYPICAL SECTION SELECTION | | |||
760 | PRELIMINARY ENGINEERING REPORT | | |||
761 | NATURAL RESOURCE EVALUATION | | |||
762 | SHPO CONSULTATION COMPLETE | | |||
763 | NMFS INFORMAL CONSULT COMP | | |||
764 | NMFS FORMAL CONSULT COMP | | |||
765 | INTERCHANGE ACCESS REPORT | | |||
801 | PREQUALIFY JPA | | |||
810 | REQUEST FOR JPA | | |||
815 | JPA WRITTEN | | |||
820 | JPA LOCAL SIGNATURE | | |||
822 | JPA EXECUTED | | |||
823 | JPA TO RAILROAD | | |||
825 | JPA ENCUMBURED/COMMITTED | | |||
851 | UTILITY DEPEND TIME TO PRJ MGR | | |||
852 | UTIILITY CONTRACT EXECUTION | | |||
853 | CONSULTANT GRANT EXECUTED | | |||
868 | JPA PREPARED | | |||
874 | LOCAL SIGNATURE | | |||
876 | STATE SIGNATURE | | |||
881 | JPA END | | |||
887 | JPA EXPIRATION IN 90 DAYS | | |||
892 | FINAL PAYMENT | | |||
901 | PH I Plans Submittal | 11301 - Prepare PH I Plans | 19901 - Update LRE Quantities - PH I (FF) 30101 - Review PH I Plans 26401 - Submittal I to Utilities | Load ERC; send out for a review. | |
902 | PH II Plans Submittal | 11302 - Prepare PH II Plans 44505 - R/W TRANSFER AGREEMENT DOCUMENTATION RECEIVED (FS-11) 16300 - MA DOCUMENTATION RECEIVED (FS-11) | 19903 - Update LRE Quantities - PH II (FF) 90701 - CONSTRUCTABILITY REVIEW 32701 - FINAL R//W REQUIREMENTS RECEIVED BY SURVEY 30201 - Review PH II Plans 28101 - NO RAIL INVOLVEMENT 27201 - SUBMIT PERMIT APPLICATIONS | Load PH II Plans in ERC; send out for a review. | |
903 | PH III Plans Submittal | 11303 - Prepare PH III Plans 27103 - Add Geotech Information 26404 - Plot SUE Data | 17101 - Contract Time Memo 37601 - ENVIRONMENTAL CERTIFICATION 30301 - Review PH III Plans 24501 - FINAL BIDABILITY REVIEW 19905 - Update Trnsport Quantities - PH III (FF) | Load PH III Plans in ERC; send out for a review. | |
904 | PH IV Plans Submittal | 11304 - Prepare PH IV Plans - (100%) | 18800 - Preliminary Engineering Certification 31001 - Review PH IV Plans / Bidability Backcheck | Load PH IV Plans in ERC; send out for a review. | |
905 | Final Plans Submittal | | |||
906 | ENTER DOCUMENTS INTO GAP | | |||
907 | CONSTRUCTABILITY REVIEW | 90201-Submit PH II Plans | 30201 - Review PH II Plans (FF) | ||
911 | Submit 30% Structures Plans | | |||
912 | Submit 60% Structures Plans | | |||
913 | Submit 90% Structures Plans | | |||
914 | Submit 100% Structures Plans | | |||
921 | NEGOTIATIONS - LAP | | |||
92203 | PREPARE DESIGN LAP AGREEMENT FOR SIGNATURE (FDOT) | | |||
922038 | RECV SIGNED LAP AGREEMENT (DESIGN) FROM �LA (FDOT) | | |||
92205 | PREPARE CONSTRUCTION LAP AGREEMENT FOR SIGNATURE (FDOT) | | |||
922058 | RECV SIGNED LAP AGREEMENT (CONST) FROM �LA (FDOT) | | |||
92206 | PREPARE CEI LAP AGREEMENT FOR SIGNATURE (FDOT) | | |||
922068 | RECV SIGNED LAP AGREEMENT (CEI) FROM �LA (FDOT) | | |||
92303 | DESIGN TWO EXECUTED (BETWEEN FDOT & DESIGN FIRM)(PH 38) | | |||
924 | DESIGN TWO EXECUTED (BETWEEN FDOT & DESIGN FIRM)(PH 48) | | |||
92505 | CONSTRUCTION CONTRACT EXECUTION (BETWEEN LA & CONTRACTOR) (PH 58) | | |||
92606 | CEI TWO EXECUTED (BETWEEN FDOT & CEI FIRM)(PH 68) | | |||
927 | PRECON MEETING - LAP | | |||
950 | DESIGN (FIRM/FDOT)/INDEPENDENT STAFF HOUR EST - LAP | | |||
95001 | LOCAL AGENCY/INDEPENDENT STAFF HOUR EST -LAP | | |||
95503 | PROJECT CLOSEOUT (PH38- LAP) | | |||
95505 | PROJECT CLOSEOUT (PH58- LAP) | | |||
95506 | PROJECT CLOSEOUT (PH68- LAP) | | |||
960 | PROJECT COMPLETE | | |||
988 | | ||||
99XX | UNFUNDED + A/E (ex. 99280) | | |||
962 | Anticipated Award Date | | |||
998 | REQUEST ESTIMATE-SCOPE,PH1+2 | |