Cost Per Mile Models Reports

Disclaimer: Cost per Mile (CpM) models are conceptual and posted for reference only. They have been created within the Long Range Estimating (LRE) application utilizing various Typical Sections available within LRE. Models are generic in nature, are modeled using formulas within LRE, and are not based on actual construction projects, past or present. Models presented may not match the scope, criteria, terrain, or other conditions of an actual construction project. They do not account for project-specific scope and characteristics, including, but not limited to the following:

  • Additional earthwork volumes beyond initial values for terrain or stormwater management facilities
  • Structures
  • Intersections
  • Driveway connections
  • Signalization
  • Right-of-way
  • Safety upgrades

Project-specific characteristics must be considered when preparing estimates for construction projects. Unit Prices within the CPM models are quantity-weighted average awarded unit prices received in the previous approximate 18 months prior to updating the CPM models. Additional FDOT unit price data can be found here.

Information: For guidance on estimating bridge costs, see Vol. 1 Chapter 9 of the Structures Manual.

ModelCost Per MileReport
Rural
New Construction Undivided 2 Lane Rural Road with 5' Paved Shoulders: R01$5,549,319.13Report
New Construction Undivided 3 Lane Rural Road with 5' Paved Shoulders, Center Turn Lane: R02$6,662,892.60Report
New Construction Undivided 4 Lane Rural Road with 5' Paved Shoulders: R03$7,688,490.95Report
New Construction Divided 4 Lane Rural Road with 2' Paved Shoulders Inside and 5' Paved Shoulders Outside: R04$10,836,671.74Report
New Construction Divided 4 Lane Rural Interstate with Paved Shoulders 10' Outside and 4' Inside: R05$13,614,948.15Report
New Construction Undivided 5 Lane Rural Road with 5' Paved Shoulders, Center Turn Lane: R06$9,173,014.74Report
New Construction Divided 6 Lane Rural Road with 5' Paved Shoulders Inside and Out: R07$12,962,811.19Report
New Construction Divided 6 Lane Rural Interstate with 10' Paved Shoulders Inside and Out: R08$15,613,376.17Report
New Construction Extra Cost for 1 Single Additional Lane on Rural Arterial: R09$1,168,629.05Report
New Construction Extra Cost for 1 Single Additional Lane on a Rural Interstate: R10$1,324,153.50Report
Mill and Resurface 2 Lane Rural Road with 5' Paved Shoulders: R11$799,143.09Report
Mill and Resurface 3 Lane Rural Road with 5' Paved Shoulders and Center Turn Lane: R12$1,108,282.20Report
Mill and Resurface 4 Lane Rural Road with 5' Paved Shoulders: R13$1,718,857.28Report
Mill and Resurface 4 Lane Divided Rural Arterial with 5' Outside Shoulders and 2' Inside: R14$1,810,288.74Report
Mill and Resurface 4 Lane Divided Rural Interstate with Paved Shoulders 10' Outside and 4' Inside: R15$2,168,129.73Report
Mill and Resurface 5 Lane Rural Road with 5' Paved Shoulders and Center Turn Lane: R16$2,076,827.91Report
Mill and Resurface 6 Lane Divided Rural Arterial with 5' Paved Shoulders Inside and Out: R17$2,592,985.71Report
Mill and Resurface 6 Lane Divided Rural Interstate with 10' Paved Shoulders Inside and Out: R18$3,102,601.84Report
Mill and Resurface 1 Additional Lane Rural Interstate: R19$511,792.17Report
Mill and Resurface 1 Additional Lane Rural Arterial: R20$410,713.87Report
Widen Existing 2 Lane Arterial to 4 Lanes Undivided; Add 1 Lane to Each Side; 5' Paved Shoulders: R21$5,265,909.31Report
Widen Existing 2 Lane Arterial to 4 Lane Divided; Resurface Existing 2 Lanes; 5' Paved Shoulders Inside and Out: R22$6,735,486.04Report
Widen Existing 4 Lane Divided Arterial to 6 Lane Divided; Resurface Existing 4 Lanes; 5' Paved Shoulders Inside and Out: R23$5,577,759.20Report
Widen 4 Lane Interstate to 6 Lanes (In Median); Mill and Resurface Existing; 10' Paved Shoulders Inside and Out: R24$8,887,313.04Report
Widen 4 Lane Interstate to 6 Lanes (Outside); Mill and Resurface Existing; 10' Shoulders Outside; Widen Existing 4' Inside Shoulders to 10': R25$8,380,928.04Report
Widen Existing 6 Lane Divided Arterial to 8 Lane Divided; Resurface Existing 6 Lanes; 5' Paved Shoulders Inside and Out: R26$6,053,110.88Report
Widen 6 Lane Interstate to 8 Lanes (in Median); Mill and Resurface Existing; 10' Paved Shoulders Inside and Out: R27$9,724,875.61Report
Widen Divided Rural 4-Lane to Allow for Left Turn Lane, 300': R28$313,430.61Report
Widen Divided Rural 4-Lane for Right Turn Lane, 300': R29$295,786.21Report
Urban
New Construction 2 Lane Undivided Urban Arterial with 4' Bike Lanes: U01$9,116,872.25Report
New Construction 3 Lane Undivided Urban Arterial with Center Lane and 4' Bike Lanes: U02$10,231,945.36Report
New Construction Undivided Urban Arterial with 4' Bike Lanes: U03$11,091,016.64Report
New Construction 4 Lane Urban Road with 22' Median and 4' Bike Lanes: U05$17,017,368.36Report
New Construction 4 Lane Divided Urban Interstate, Closed 22' Median with Barrier Wall, 10' Shoulders Inside and Out: U06$23,894,351.64 Report
New Construction 5 Lane Undivided Urban Arterial with Center Turn Lane and 4' Bike Lanes: U07$12,822,124.28 Report
New Construction 6 Lane Urban Road with 22' Median and 4' Bike Lanes: U08$18,549,372.01Report
New Construction 6 Lane Divided Urban Interstate with 22' Closed Median with Barrier Wall, 10' Shoulders Inside and Out: U09$25,793,473.60 Report
New Construction Extra Cost for Additional Lane on Urban Arterial: U10$4,420,437.82Report
New Construction Extra Cost for Additional Lane on Urban Interstate: U11$1,419,871.49Report
Mill and Resurface 2 Lane Urban Road with 4' Bike Lanes: U12$911,865.84Report
Mill and Resurface 3 Lane Urban Road with Center Turn Lane and 4' Bike Lanes: U13$1,186,248.73Report
Mill and Resurface 4 Lane Undivided Urban Roadway with 4' Bike Lanes: U14$1,606,864.17Report
Mill and Resurface 4 Lane Divided Urban Roadway with 4' Bike Lanes: U15$1,882,576.27Report
Mill and Resurface 5 Lane Urban Roadway with Center Turn Lane and 4' Bike Lanes: U16$1,888,808.08Report
Mill and Resurface 6 Lane Divided Urban Arterial with 4' Bike Lanes: U17$2,736,124.28Report
Mill and Resurface 1 Additional Lane Urban Arterial: U18$448,024.86Report
Add 2 Lanes to Existing 2 Lane Undivided Arterial (1 Lane Each Side), with 4' Bike Lanes: U19$9,540,676.51Report
Widen 2 Lane Urban Arterial to 4 Lane Divided with 22' Median, 4' Bike Lanes: U20$11,479,370.51Report
Add 2 Lanes to Existing 3 Lane Undivided Arterial (1 Lane Each Side with Center Turn Lane and 4' Bike Lanes: U21$9,847,437.67Report
Widen 4 Lane Urban Divided Arterial to 6 Lane Urban Divided with 22' Median and 4' Bike Lanes: U22$9,302,864.82Report
Widen 4 Lane Urban Interstate with Closed Median to 6 Lanes (Outside), Mill and Resurface Existing, 10' Shoulders Outside: U23$15,978,893.72Report
Widen 6 Lane Urban Divided Arterial to 8 Lane Urban Divided with 4' Bike Lanes: U24$11,415,171.18Report
Widen 6 Lane Urban Interstate with Closed Median to 8 Lanes (Outside); Mill and Resurface Existing; 10' Shoulders Outside: U25$17,127,313.20Report
Suburban
New Construction Suburban 4 Lane with Paved Shoulders Outside and Curb Median: S01$10,458,281.48Report
Widen Existing Rural Facility to the Inside with Addition of Closed Drainage System and Median Barrier Wall: S02$6,274,731.41Report
Widen 4 Lane Suburban Roadway with 6.5' Paved Shoulder and Convert to Curb and Gutter Out; Stripe for Bike Lane: S03$5,312,531.89Report
Add 2 Lanes with Curb and Gutter Out to Existing 4 Lane Urban or Suburban Roadway with Curb and Gutter Out: S04$5,492,128.56Report
Other
Two Directional, 12' Shared Use Path: O01$681,822.62Report
Rails to Trails project (12' width): O02$634,555.69Report
Sidewalk construction; 5' one side, 4-inch depth: O03$349,251.29Report
Mid-Block Crossing: O05$285,450.86Report

 