July 2022 Workbook


Implemented Modifications to the 2022 Standard Specifications

July 2022 Workbook

for Lettings Effective July 1,2022 - June 30,2023


Special Provisions -Specific clauses adding to or revising the Standard Specifications, setting forth conditions varying from or additional to the Standard Specifications for a specific project.

Supplemental Specifications - Additions or revisions to the Standard Specifications.

History of Revisions - To review the History of revisions for this Workbook.

Mandatory Revisions - Critical modifications implemented for the Workbook.

 

Note: These files are in Adobe Acrobat (PDF) format.

File size ranges from 9 kb to 200 kb.

SPECIAL PROVISIONSSpec NameUsage Note
PROPOSAL REQUIREMENTS AND CONDITIONS (BUSINESS DEVELOPMENT INITIATIVE).
(REV 4-21-16) (FA 4-21-16) (7-22)

Changes to: 2-1, 2-7.
SP0020100BDIUse with the approval of the District Program Management Office.
Use with SP0030201BDI, SP0071302BDI and SP0080100BDI.
PROPOSAL REQUIREMENTS AND CONDITIONS - EXAMINATION OF PLANS, SPECIFICATIONS, SPECIAL PROVISIONS, AND SITE OF WORK.
(REV 6-16-21) (FA 8-2-21) (7-22)

Insert Information Required.
Changes to: 2-4.
SP0020400All Jobs (add a phone number or email address)
Do not use withSP0020400-60day.
PROPOSAL REQUIREMENTS AND CONDITIONS - EXAMINATION OF PLANS, SPECIFICAITONS, SPECIAL PROVISIONS, AND SITE OF WORK (60 DAY AD).
(REV 6-16-21) (FA 8-2-21) (7-22)

Insert Information Required.
Changes to: 2-4.
SP0020400-60day Jobs with 60-day Ads. (add a phone number or email address)
Do not use withSP0020400.
PROPOSAL REQUIREMENTS AND CONDITIONS - PREPARATION OF PROPOSALS (A+B BIDDING).
(REV 6-22-04) (FA 7-13-04) (7-22)

Changes to: 2-5.1.
SP0020501AB
A+B Bidding. Use with the approval of the District Construction Engineer.
Use with SP0030100AB, SP0030203AB,SP0080701AB and SP0081300AB.
PROPOSAL REQUIREMENTS AND CONDITIONS - PREPARATION OF PROPOSALS (LANE RENTAL).
(REV 2-21-05) (FA 3-31-05) (7-22)

Insert Information Required.
Changes to: 2-5.1.
SP0020501LRLane Rental. Use with the approval of the District Construction Engineer.
Use with SP0030100LR, SP0081300LRDR and SP0081300LR.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS - SCOPE ALTERNATES.
(REV 11-3-15) (FA 11-20-15) (7-22)

Changes to: 3-1.
SP0030100
Use at the direction of the District Construction Engineer in accordance with the Work Program Instructions.
*Notify Contracts Office on Transmittal Memo.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (A+B BIDDING).
(REV 11-5-97) (FA 1-20-98) (7-22)

Insert Information Required
Changes to: 3-1.
SP0030100ABA+B Bidding. Use with the approval of the District Construction Engineer.
Use with SP0020501AB, SP0030203AB, SP0080701AB and SP0081300AB.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (BUDGETARY CONSTRAINTS).
(REV 11-3-15) (FA 11-20-15) (7-22)

Insert Information Required
Changes to: 3-1.
SP0030100BC Use at the direction of the District Construction Engineer in accordance with the Work Program Instructions.
*Notify the Contracts Administration Office on the Transmittal Memo.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (LANE RENTAL).
(REV 11-3-15) (FA 11-20-15) (7-22)

Changes to: 3-1.
SP0030100LRLane Rental. Use with the approval of the District Construction Engineer.
Use with SP0020501LR, SP0081300LR and SP0081300LRDR.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (LUMP SUM).
(REV 8-1-00) (7-22)

Changes to: 3-1.
SP0030100LSLump Sum Projects.
AWARD AND EXECUTION OF CONTRACT (TIMEFRAME MODIFICATION).
(REV 3-2-17) (FA 4-27-17) (7-22)

Insert Information Required
Changes to: 3-2, 3-6, 3-7.
SP0030200Use when modifying the “Award and Execution” timeframes in the Standard Specifications.
*Contracts Office must approve.
AWARD AND EXECUTION OF CONTRACT (BUSINESS DEVELOPMENT INITIATIVE).
(REV 10-3-19) (FA 11-25-19)(7-22)

Changes to: 3-2.1, 3-2.2, 3-6, 3-7.
SP0030201BDIUse with the approval of the District Program Management Office.
Use with SP0020100BDI, SP0071302BDI, and SP0080100BDI.
AWARD AND EXECUTION OF CONTRACT - AWARD OF CONTRACTS (A+B BIDDING)
(REV 8-22-96) (FA 9-3-96) (7-22)

Insert Information Required
Changes to: 3-2.
SP0030203AB A+B Bidding. Use with the approval of the District Construction Engineer.
Use with SP0020501AB, SP0030100AB, SP0080701AB, and SP0081300AB.
AWARD AND EXECUTION OF CONTRACT - PUBLIC RECORDS
(REV 10-17-16) (FA 10-24-16 ) (7-22)

Changes to: 3-9.
SP0030900All Jobs.
SCOPE OF THE WORK - INTENT OF CONTRACT.
(REV 10-25-21) (FA 1-26-22) (7-22)

Insert Information Required.
Changes to: 4-1.
SP0040100All Jobs, excluding Lump Sum.
SCOPE OF THE WORK (LUMP SUM).
(REV 6-3-16) (FA 6-9-16) (7-22)

Insert Information Required.
Changes to: 4-1, 4-3.1, 4-3.4, 4-3.9.4.
SP0040100LSLump Sum Projects.
CONTROL OF THE WORK (LUMP SUM).
(REV 3-15-02) (7-22)

Changes to: 5-1.1, 5-2, 5-7.6.
SP0050101LSLump Sum Projects.
CONTROL OF MATERIALS - ACCEPTANCE CRITERIA (LUMP SUM).
(REV 8-17-09) (FA 8-24-09) (7-22)

Changes to: 6-1.
SP0060100LSLump Sum Projects.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED (COMPLIANCE WITH FHWA 1273).
(REV 1-2-14) (1-16-14) (7-22)

Changes to: 7-1.1.
SP0070101Use in all Federal Aid Jobs with letting dates prior to September 1, 2022. Do not use with SP0070101-722.

LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED (COMPLIANCE WITH FHWA-1273)

Changes to: 7-1.1

SP0070101-722Implemented by Mandatory No. 1. Use in all Federal Aid jobs with lettings from September 1, 2022 and later. 
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BEAR).
(REV 6-6-17) (FA 6-13-17) (7-22)

Changes to: 7-1.4.
SP0070104-1Use when called for by the District Environmental Permit Office (Bear)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BALD EAGLE).
(REV 6-16-17) (FA 6-28-17) (7-22)

Changes to: 7-1.4.
SP0070104-2Use when called for by the District Environmental Permit Office ( Bald Eagle)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (GOPHER TORTOISE).
(REV 6-15-17) (FA 6-20-17) (7-22)

Changes to: 7-1.4.
SP0070104-3Use when called for by the District Environmental Permit Office (Gopher Tortoise)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (MANATEE).
(REV 5-13-20) (FA 6-29-20) (7-22)

Changes to: 7-1.4.
SP0070104-4Use when called for by the District Environmental Permit Office (Manatee)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SMALLTOOTH SAWFISH).
(REV 10-21-21) (FA 1-6-22) (7-22)

Changes to: 7-1.4.
SP0070104-5Use when called for by the District Environmental Permit Office (Smalltooth Sawfish)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SEA TURTLE).
(REV 10-21-21) (FA 1-6-22) (7-22)

Changes to: 7-1.4.
SP0070104-6Use when called for by the District Environmental Permit Office (Sea Turtle)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (INDIGO SNAKE).
(REV 5-25-17) (FA 6-13-17) (7-22)

Changes to: 7-1.4.
SP0070104-7Use when called for by the District Environmental Permit Office (Indigo Snake)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (STURGEON).
(REV 6-24-20) (FA 8-24-20) (7-22)

Changes to: 7-1.4.
SP0070104-8Use when called for by the District Environmental Permit Office (Sturgeon)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SEAGRASS BEDS)
(REV 10-3-18) (FA 12-11-18) (7-22)

Changed to: 7-1.4.
SP0070104-9 Used when called for by the District Environmental Permit Office (Seagrass Beds)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BATS)
(REV 12-7-18) (FA 1-4-19) (7-22)

Changed to: 7-1.4.
SP0070104-10Used when called for by the District Environmental Permit Office (Bats)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BATS IN BRIDGES) 
(REV 12-7-18) (12-11-18) (7-22)

Changed to: 7-1.4.
SP0070104-11Used when called for by the District Environmental Permit Office (Bats in Bridges)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC – LAWS TO BE OBSERVED – COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SCRUB-JAYS)
(REV 5-14-20) (FA 7-7-20) (7-22)

Changed to: 7-1.4.
SP0070104-12

Use when called for by the District Environmental Permit Office (Scrub-Jays)

LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PERMITS AND LICENSES (PERMITS PROCURED BY THE DEPARTMENT).
(REV 11-10-16) (FA 1-26-17) (7-22)

Changes to: 7-2.1.
SP0070201AJobs with permits procured by DOT.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY (TOLL FACILITIES).
(REV 7-22-14) (FA 10-15-14) (7-22)

Changes to: 7-11.1, 7-11.2.
SP0071101-tollsUse with the approval of the District Traffic Operations Engineer.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - FLORIDA GAS TRANSMISSION COMPANY, LLC (FGT) FACILITIES.
(REV 4-6-16) (FA 4-20-16) (7-22)

Changes to: 7-11.5.
SP0071105FGTUse when Florida Gas Transmission Company, LLC (FGT) is within the project limits.
Use with SP0071201FGT.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - UTILITY ADJUSTMENTS (NO UTILITY WORK SCHEDULE).
(REV 2-10-94) (7-22)

Changes to: 7-11.5.3.
SP0071153AWhen there are no utility work schedules.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - UTILITY ADJUSTMENTS (UTILITY WORK SCHEDULES).
(REV 1-26-22) (FA 2-3-22) (7-22)

Changes to: 7-11.5.1, 7-11.5.3.
SP0071153BWhen there are utility work schedules.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC (FLORIDA GAS TRANSMISSION (FGT) COMPANY, LLC ENCROACHMENT AGREEMENTS).
(REV 7-28-15) (FA 7-31-15) (7-22)

Changes to: 7-12.1, 7-13.2, 7-13.4.
SP0071201FGTUse when Florida Gas Transmission Company, LLC (FGT) is within the project limits.
Use with SP0071105FGT.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - INSURANCE - COMMERCIAL GENERAL LIABILITY INSURANCE (BUSINESS DEVELOPMENT INITIATIVE).
(REV 4-10-15) (FA 7-31-15) (7-22)

Changes to: 7-13.2
SP0071302BDIUse with the approval of the District Program Management Office.
Use with SP0020100BDI, SP0030201BDI, and SP0080100BDI.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC -CSXT RAILROAD INSURANCE REQUIREMENTS
(REV 5-4-20) (FA 8-24-20) (7-22)

Changes to: 7-13.3.
SP0071303When requested by the District Rail Office.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - WAGE RATES FOR FEDERAL-AID PROJECTS.
(REV 9-1-17) (FA 10-31-17) (7-22)

Insert Information Required.
Changes to: 7-16.
SP0071600All Federal Aid Jobs.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS.
(REV 4-25-02) (FA 7-17-02) (7-22)

Changes to: Section 7.
SP0072700Non-Federal Aid Projects.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PREFERENCE TO STATE RESIDENTS.
(REV 1-13-12) (7-22)

Changes to: Section 7.
SP0072800Non-Federal Aid Projects.
Construction Projects Only.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC -        E-VERIFY.
(REV 6-13-11) (FA 6-16-11) (7-22)

Changes to: Section 7.
SP0072900All Jobs.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - SCRUTINIZED COMPANIES.
(REV 3-22-18) (7-22)

Changes to: Section 7.
SP0073000All Jobs.
           
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - TITLE VI ASSURANCE - DOT 1050.2, APPENDIX A and APPENDIX E.
(REV 5-27-16) (FA 6-2-16) (7-22)

Changes to: Section 7.
SP0073100All Federally Funded Jobs.
PROSECUTION AND PROGRESS - SUBLETTING OR ASSIGNING  OF CONTRACTS (BUSINESS DEVELOPMENT INITIATIVE).
(REV 4-21-15) (FA 7-13-15) (7-22)

Changes to: 8-1.
SP0080100BDIUse with the approval of the District Program Management Office.
Use with SP0020100BDI, SP0030201BDI, and SP0071302BDI.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK (SUBMISSION OF WORKING SCHEDULE).
(REV 5-20-21) (FA 7-7-21) (7-22)

Changes to: 8-3.2.
SP0080302AUse only when CPM is authorized by District Construction Engineer.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (FLEXIBLE START TIME).
(REV 3-2-17) (FA 4-27-17) (7-22)

Insert Information Required
Changes to: 8-3.3.
SP0080303AWhen called for by the District Construction Engineer or the District Maintenance Engineer/Administrator.
*Contracts Office must be notified.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (NOTICE TO PROCEED).
(REV 3-2-17) (FA 4-27-17) (7-22)

Insert Information Required
Changes to: 8-3.3.
SP0080303BWhen called for by the District Construction Engineer.
Use with the approval of the Director, Office of Construction.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (MANDATORY START DATE).
(REV 3-2-17) (FA 4-27-17) (7-22)

Insert Information Required.
Changes to: 8-3.3.
SP0080303CWhen called for by the District Construction Engineer.
Use with the approval of the Director, Office of Construction.
*Contracts Office must be notified.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - PARTNERING.
(REV 5-15-12) (FA 5-21-12) (7-22)

Insert Information Required.
Changes to: 8-3.
SP0080306 Jobs with 999-16 Pay Items
*Contracts Office must be notified.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - DISPUTES REVIEW BOARD.
(REV 2-9-21) (FA 2-18-21) (7-22)

Changes to: 8-3.
SP0080307DRBJobs with 999-20 Pay Items
*Contracts Office must be notified.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - REGIONAL DISPUTES REVIEW BOARD.
(REV 2-8-21) (FA 2-18-21) (7-22)

Changes to: 8-3.
SP0080307RDRBJobs without 999-20 Pay Items.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - STATEWIDE DISPUTES REVIEW BOARD.
(REV 6-27-19 ) (FA 8-14-19) (7-22)

Changes to: 8-3.
SP0080308SDRBJobs with 334, 337, 350, 570 or 649 Pay Items.
PROSECUTION AND PROGRESS – COMPUTATION OF CONTRACT TIME – ADJUSTING CONTRACT TIME – INCREASED WORK (LUMP SUM).
(REV 8-1-00) (7-22)

Changes to: 8-4.1, 8-7.3.1.
SP0080401LSLump Sum Projects
 PROSECUTION AND PROGRESS – LIMITATIONS OF OPERATIONS – NIGHT WORK ALONG COASTAL ROADS.
(REV 4-8-19) (FA 7-22-19) (7-22)

Changes to: 8-4.1
 SP0080401Use when requested by the District Environmental Office
PROSECUTION AND PROGRESS - LIMITATIONS OF OPERATIONS - FENCING.
(REV 6-17-04) (FA 7-13-04) (7-22)

Changes to: 8-4.8.
SP0080408Jobs on Limited Access Highways
PROSECUTION AND PROGRESS - LIMITATIONS OF OPERATIONS - CONTAMINATED MATERIAL (MERCURY-CONTAINING DEVICES AND LAMPS).
(REV 11-6-95) (FA 12-27-95) (7-22)

Insert Information Required.
Changes to: 8-4.9.
SP0080409Jobs with Lighting

PROSECUTION AND PROGRESS - SUSPENSION OF CONTRACTOR'S OPERATIONS - SPECIAL EVENTS.
(REV 5-21-21) (FA 1-3-22) (7-22)

Insert Information Required. Changes to: 8-6.4.
SP0080604Use on jobs with Special Events.
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (REDUCED PRODUCTIVITY).
(REV 12-22-98) (FA 1-19-99) (7-22)

Insert Information Required.
Changes to: 8-7.1.
SP0080701AUse with approval of the District Construction Engineer.
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (A+B BIDDING).
(REV 7-24-96) (FA 9-3-96) (7-22)

Changes to: 8-7.1.
SP0080701ABA+B Bidding. Use with the approval of the District Construction Engineer.
Use with SP0020501AB, SP0030100AB,SP0030203AB, and SP0081300AB.
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (SHORTENED CONTRACT TIME).
(REV 2-14-94) (7-22)

Insert Information Required.
Changes to: 8-7.1.
SP0080701BUse with the approval of the Director, Office of Construction.
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (HIGHER PRODUCTION RATES).
(REV 12-22-98) (FA 2-1-99) (7-22)

Changes to: 8-7.1.
SP0080701CUse when requested by the District Construction Engineer.
PROSECUTION AND PROGRESS - LIQUIDATED DAMAGES FOR FAILURE TO COMPLETE THE WORK.
(REV 4-2-19) (FA 9-23-19) (7-22)

Insert Information Required.
Changes to: Section 8-10.1, 8-10-2.
SP0081000Use on all revenue producing projects.
PROSECUTION AND PROGRESS - DAMAGE RECOVERY.
(REV 8-7-17) (7-22)

Insert Information Required.
Changes to: 8-12.
SP0081200Use when requested by the District Construction Engineer.
(Do not use with Lane Rental)
PROSECUTION AND PROGRESS - ALTERNATIVE BIDDING.
(REV 7-28-97) (7-22)

Changes to: Section 8.
SP0081300AAll Jobs with Alternative Bidding. Use with the approval of the District Construction Engineer.
8-13. INCENTIVE - DISINCENTIVE FOR A+B.
(REV 7-27-04) (FA 7-28-04) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300ABA+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030100AB, SP0030203AB, and SP0080701AB.
8-13.  "BONUS" PAYMENT AND WAIVER OF CONTRACTOR CLAIMS.

(REV 5-19-04) (FA 7-13-04) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300ABBA+B Jobs with Bonus Use with the approval of the District Construction Engineer.
8-13. " BONUS " PAYMENT AND WAIVER OF CONTRACTOR CLAIMS.
(REV 7-27-04) (FA 7-28-04) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300BBonus (Date Specific) Use with the approval of the District Construction Engineer.
8-13. "BONUS" PAYMENT AND WAIVER OF CONTRACTOR CLAIMS.
(REV 7-27-04) (FA 7-28-04) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300BCDBonus (Calendar Days) Use with the approval of the District Construction Engineer.
8-13.INCENTIVE - DISINCENTIVE.
(REV 7-27-04) (FA 7-28-04) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300IDIncentive - Disincentive. Use with the approval of the District Construction Engineer. Do not use with SP0081300MID.
8-13.INCENTIVE - DISINCENTIVE FOR LANE RENTAL DAYS.
(REV 9-25-03) (FA 12-24-03) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300IDLRIncentive-Disincentive for Lane Rental Days. Use with the approval of the District Construction Engineer. Do not use with SP0081300LR or SP0081300LRDR.
8-13. LIQUIDATED SAVINGS FOR EARLY COMPLETION.
(REV 5-18-99) (FA 6-10-99) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300LQSLiquidated Savings. Use with the approval of the District Construction Engineer.
8-13. PAY ADJUSTMENT FOR FEWER-MORE LANE RENTAL DAYS.
(REV 4-29-97) (FA 5-7-97) (7-22)

Changes to: 8-13.
SP0081300LRLane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0030100LR, and SP0081300LRDR.
8-13. DAMAGE RECOVERY.
(REV 9-25-03) (FA 12-24-03) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300LRDRLane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0030100LR, and SP0081300LR.
8-13. “BONUS” PAYMENT AND WAIVER OF CONTRACTOR CLAIMS.
(REV 4-12-06) (FA 4-25-06) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300MBMilestone Bonus Use with the approval of the District Construction Engineer. Do not use with SP0081300B or SP0081300BCD.
8-13. INCENTIVE - DISINCENTIVE.
(REV 2-9-06) (FA 4-25-06) (7-22)

Insert Information Required.
Changes to: 8-13.
SP0081300MIDMilestone Incentive-Disincentive. Use with the approval of the District Construction Engineer. Do not use with SP0081300ID.
MEASUREMENT AND PAYMENT (LUMP SUM).
(REV 7-1-21) (FA 7-28-21) (7-22)

Changes to: 9-1.3, 9-2, 9-3, 9-5.5.2, 9-11.
SP0090103LSLump Sum Projects.
MOBILIZATION (LUMP SUM) 
(REV 10-17-19) (FA 11-25-19) (7-22)

SP1010000LSLump Sum Projects.
CLEARING AND GRUBBING - REMOVAL OF EXISTING BRIDGES - GENERAL.
(REV 9-10-07) (FA 2-15-08) (7-22)

Insert Information Required.
Changes to: 110-6.1.
SP1100601Use when requested by the District Construction Engineer. Must have signed agreement from the Local Agency receiving the material.
CLEARING AND GRUBBING - REMOVAL OF EXISTING BRIDGES - ASBESTOS CONTAINING MATERIALS (ACM) IDENTIFIED PRIOR TO THE WORK.
(REV 11-10-16) (FA 1-26-17) (7-22)

Changes to: 110-6.
SP1100606Use when areas of Asbestos Abatement are identified in the Plans.
CLEARING AND GRUBBING (MATERIAL FOR REEF ESTABLISHMENT).
(REV 7-10-95) (FA 6-21-99) (7-22)

Changes to: 110-11.7, 110-12.7.
SP1101107Jobs with 110-84 Pay Item.
EXCAVATION AND EMBANKMENT - DESCRIPTION - IDENTIFIED AREAS OF CONTAMINATION.
(REV 11-10-16) (FA 1-26-17 ) (7-22)

Changes to: 120-1.
SP1200100AUse when contaminated areas are delineated in the Plans.
MILLING OF EXISTING ASPHALT PAVEMENT.
(REV 8-31-99) (FA 2-14-00) (7-22)

Insert Information Required.
Changes to: 327-1, 327-6.
SP3270100When the Plans provide a location for stockpiling milled material. Insert quantity to be retained. Use "all, tons, square yards", etc.
MILLING OF EXISTING ASPHALT PAVEMENT - EQUIPMENT.
(REV 12-1-93) (7-22)

Changes to: 327-2.
SP3270200Use when requested by the District.
MILLING OF EXISTING ASPHALT PAVEMENT
(REV 12-16-19) (FA 12-30-19) (7-22)

Changes to: 327-3.
SP3270301Use with approval from the District Construction Engineer.
HOT MIX ASPHALT - GENERAL CONSTRUCTION REQUIREMENTS.
(REV 2-22-18) (FA 2-22-18) (7-22)

Changes to: 330-8.2, 330-9.4, 330-9.5.1
SP3300802 Use on all interstate and limited access asphalt pavement roadway projects.

SUPERPAVE ASPHALT CONCRETE 

(REV 5-4-21) (FA 7-14-21) (7-22)

Changes to: 334-2.3.4

SP3340203Use on projects with available coring data.
CEMENT CONCRETE PAVEMENT (COLORED CONCRETE).
(REV 5-11-16) (FA 5-12-16) (7-22)

Changes to: 350-1, 350-2, 350-11.
SP3500200Use when the Plan
pay item 350-30 or Colored Concrete is included.
INTEGRAL PILE AND COLUMN JACKETS.
(REV 11-22-19) (FA 1-27-20) (7-22)

Changes to: 457.
SP4570000Jobs with 457 Pay Items
LANDSCAPING.
(REV 10-30-19) (FA 1-7-20) (7-22)

Changes to: 580.
SP5800000Non-Federal Aid Jobs with Landscaping.
Use when requested by the DDE.
LANDSCAPING.
(REV 5-11-21) (FA 7-14-21) (7-22)

Changes to: 580.
SP5800000FA  All Federal Aid Jobs with Landscaping.
Use when requested by the DDE.
TREE AND PALM RELOCATION - CONSTRUCTION.
(REV 7-13-21) (FA 7-14-21) (7-22)
SP5810000Jobs with Tree and Palm Relocation.
ELECTRICAL POWER SERVICE ASSEMBLIES - DESCRIPTION (Contribution-in-Aid-of Construction).
(REV 6-12-18) (FA 7-2-18) (7-22)

Changes to 639.
SP6390100CIACUse with approval of the District Utility Administrator.
HIGHWAY ADVISORY RADIO.
(REV 10-16-15) (FA 12-31-15) (7-22)

SP6870000Use with the approval of the Chief Engineer.
   
Supplemental SpecificationsSupplemental Spec NameUsage Note

MAINTENANCE OF TRAFFIC.

(REV 8-17-22) (10-22)

Changes to 102-3.

SS1020300Implemented by Mandatory No.2. Use on all Construction Jobs with lettings from October 1, 2022, and later. 

CONTRACTOR QUALITY CONTROL GENERAL REQUIREMENTS.

(REV 8-17-22) (10-22)

Changes to 105-8.3.

SS1050803Implemented by Mandatory No.2. Use on all Construction Jobs with lettings from October 1, 2022, and later. 

MAINTENANCE OF TRAFFIC.

(REV 2-17-22) (FA 9-9-22) (1-23)

Changes to 102-11.13, 102-11.14, 102-11.15, and 102-11.16

SS1021113Implemented by Mandatory No.3. Use on all Jobs with letting from January 1, 2023, and later.

CONTROL OF MATERIALS.

(REV 12-5-22) (FA 12-5-22) (1-23)

Changes to 6-1.3.1.1, 6-5

SS0060103Implemented by Mandatory No.4. Use on all Construction, LAP, and Federally Funded Maintenance Jobs from January 1 ,2023, and later.
   
Technical Special ProvisionsTSP NameUsage Note
The following Technical Special Provisions are individually signed and sealed but are included as part of this Specifications Package.   XTSPsJobs with Tsps.