January 2022 Workbook
Implemented Modifications to the 2022 Standard Specifications
July 2022 Workbook
for Lettings Effective July - December 2022
Special Provisions -Specific clauses adding to or revising the Standard Specifications, setting forth conditions varying from or additional to the Standard Specifications for a specific project.
Supplemental Specifications - Additions or revisions to the Standard Specifications.
History of Revisions - To review the History of revisions for this Workbook.
Mandatory Revisions - Critical modifications implemented for the Workbook.
Note: These files are in Adobe Acrobat (PDF) format.
File size ranges from 9 kb to 200 kb.
SPECIAL PROVISIONS | SP0000001 | Usage Note |
---|---|---|
PROPOSAL REQUIREMENTS AND CONDITIONS (BUSINESS DEVELOPMENT INITIATIVE). (REV 4-21-16) (FA 4-21-16) (7-22) Changes to: 2-1, 2-7. |
| Use with the approval of the District Program Management Office. Use with SP0030201BDI, SP0071302BDI and SP0080100BDI. |
PROPOSAL REQUIREMENTS AND CONDITIONS - EXAMINATION OF PLANS, SPECIFICATIONS, SPECIAL PROVISIONS, AND SITE OF WORK. (REV 6-16-21) (FA 8-2-21) (7-22) Insert Information Required. Changes to: 2-4. |
SP0020400 | All Jobs (add a phone number or email address) Do not use withSP0020400-60day |
PROPOSAL REQUIREMENTS AND CONDITIONS - EXAMINATION OF PLANS, SPECIFICAITONS, SPECIAL PROVISIONS, AND SITE OF WORK (60 DAY AD). (REV 6-16-21) (FA 8-2-21) (7-22) Insert Information Required. Changes to: 2-4. |
SP0020400-60day | Jobs with 60-day Ads. (add a phone number or email address) Do not use withSP0020400 |
PROPOSAL REQUIREMENTS AND CONDITIONS - PREPARATION OF PROPOSALS (A+B BIDDING). (REV 6-22-04) (FA 7-13-04) (7-22) Changes to: 2-5.1. | A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0030100AB, SP0030203AB,SP0080701AB and SP0081300AB. | |
PROPOSAL REQUIREMENTS AND CONDITIONS - PREPARATION OF PROPOSALS (LANE RENTAL). (REV 2-21-05) (FA 3-31-05) (7-22) Insert Information Required. Changes to: 2-5.1. |
| Lane Rental. Use with the approval of the District Construction Engineer. Use with SP0030100LR, SP0081300LRDR and SP0081300LR. |
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS - SCOPE ALTERNATES. (REV 11-3-15) (FA 11-20-15) (7-22) Changes to: 3-1. |
| Use at the direction of the District Construction Engineer in accordance with the Work Program Instructions. *Notify Contracts Office on Transmittal Memo. |
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (A+B BIDDING). (REV 11-5-97) (FA 1-20-98) (7-22) Insert Information Required Changes to: 3-1. | A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030203AB, SP0080701AB and SP0081300AB. | |
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (BUDGETARY CONSTRAINTS). (REV 11-3-15) (FA 11-20-15) (7-22) Insert Information Required Changes to: 3-1. | Use at the direction of the District Construction Engineer in accordance with the Work Program Instructions. *Notify the Contracts Administration Office on the Transmittal Memo. | |
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (LANE RENTAL). (REV 11-3-15) (FA 11-20-15) (7-22) Changes to: 3-1. |
| Lane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0081300LR and SP0081300LRDR. |
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (LUMP SUM). (REV 8-1-00) (7-22) Changes to: 3-1. |
| Lump Sum Projects |
AWARD AND EXECUTION OF CONTRACT (TIMEFRAME MODIFICATION). (REV 3-2-17) (FA 4-27-17) (7-22) Insert Information Required Changes to: 3-2, 3-6, 3-7. | Use when modifying the “Award and Execution” timeframes in the Standard Specifications. *Contracts Office must approve. | |
AWARD AND EXECUTION OF CONTRACT (BUSINESS DEVELOPMENT INITIATIVE). (REV 10-3-19) (FA 11-25-19)(7-22) Changes to: 3-2.1, 3-2.2, 3-6, 3-7. |
| Use with the approval of the District Program Management Office. Use with SP0020100BDI, SP0071302BDI, and SP0080100BDI. |
AWARD AND EXECUTION OF CONTRACT - AWARD OF CONTRACTS (A+B BIDDING) (REV 8-22-96) (FA 9-3-96) (7-22) Insert Information Required Changes to: 3-2. |
| A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030100AB, SP0080701AB, and SP0081300AB. |
AWARD AND EXECUTION OF CONTRACT - PUBLIC RECORDS (REV 10-17-16) (FA 10-24-16 ) (7-22) Changes to: 3-9. |
| All Jobs. |
SCOPE OF THE WORK - INTENT OF CONTRACT. (REV 8-19-09) (FA 8-24-09) (7-22) Insert Information Required. Changes to: 4-1. |
| All Jobs, excluding Lump Sum. |
SCOPE OF THE WORK (LUMP SUM). (REV 6-3-16) (FA 6-9-16) (7-22) Insert Information Required. Changes to: 4-1, 4-3.1, 4-3.4, 4-3.9.4. |
| Lump Sum Projects |
CONTROL OF THE WORK (LUMP SUM). (REV 3-15-02) (7-22) Changes to: 5-1.1, 5-2, 5-7.6. |
| Lump Sum Projects |
CONTROL OF MATERIALS - ACCEPTANCE CRITERIA (LUMP SUM). (REV 8-17-09) (FA 8-24-09) (7-22) Changes to: 6-1. |
| Lump Sum Projects |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED (COMPLIANCE WITH FHWA 1273). (REV 1-2-14) (1-16-14) (7-22) Changes to: 7-1.1. |
| All Federal Aid Jobs |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BEAR). (REV 6-6-17) (FA 6-13-17) (7-22) Changes to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Bear) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (EAGLE). (REV 6-16-17) (FA 6-28-17) (7-22) Changes to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Eagle) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (GOPHER TORTOISE). (REV 6-15-17) (FA 6-20-17) (7-22) Changes to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Gopher Tortoise) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (MANATEE). (REV 5-13-20) (FA 6-29-20) (7-22) Changes to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Manatee) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SAWFISH). (REV 5-25-17) (FA 6-13-17) (7-22) Changes to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Sawfish) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SEA TURTLE). (REV 5-25-17) (FA 6-28-17) (7-22) Changes to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Sea Turtle) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (INDIGO SNAKE). (REV 5-25-17) (FA 6-13-17) (7-22) Changes to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Indigo Snake) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (STURGEON). (REV 6-24-20) (FA 8-24-20) (7-22) Changes to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Sturgeon) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SEAGRASS BEDS) (REV 10-3-18) (FA 12-11-18) (7-22) Changed to: 7-1.4. |
| Used when called for by the District Environmental Permit Office (Seagrass Beds) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BATS) (REV 12-7-18) (FA 1-4-19) (7-22) Changed to: 7-1.4. |
| Used when called for by the District Environmental Permit Office (Bats) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BATS IN BRIDGES) (REV 12-7-18) (12-11-18) (7-22) Changed to: 7-1.4. |
| Used when called for by the District Environmental Permit Office (Bats in Bridges) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC – LAWS TO BE OBSERVED – COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SCRUB-JAYS) (REV 5-14-20) (FA 7-7-20) (7-22) Changed to: 7-1.4. |
| Use when called for by the District Environmental Permit Office (Scrub- Jays) |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PERMITS AND LICENSES (PERMITS PROCURED BY THE DEPARTMENT). (REV 11-10-16) (FA 1-26-17) (7-22) Changes to: 7-2.1. |
| Jobs with permits procured by DOT |
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY (TOLL FACILITIES). (REV 7-22-14) (FA 10-15-14) (7-22) Changes to: 7-11.1, 7-11.2. |
| Use with the approval of the District Traffic Operations Engineer. |
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - FLORIDA GAS TRANSMISSION COMPANY, LLC (FGT) FACILITIES. (REV 4-6-16) (FA 4-20-16) (7-22) Changes to: 7-11.5. |
| Use when Florida Gas Transmission Company, LLC (FGT) is within the project limits. Use with SP0071201FGT. |
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - UTILITY ADJUSTMENTS (NO UTILITY WORK SCHEDULES). (REV 2-10-94) (7-22) Changes to: 7-11.5.3. |
| When there are no utility work schedules. |
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - UTILITY ADJUSTMENTS (UTILITY WORK SCHEDULES). (REV 11-10-16) (FA 1-26-17) (7-22) Changes to: 7-11.5.3. |
| When there are utility work schedules. |
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC (FLORIDA GAS TRANSMISSION (FGT) COMPANY, LLC ENCROACHMENT AGREEMENTS). (REV 7-28-16) (FA 7-31-15) (7-22) Changes to: 7-12.1, 7-13.2, 7-13.4. |
| Use when Florida Gas Transmission Company, LLC (FGT) is within the project limits. Use with SP0071105FGT. |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - INSURANCE - COMMERCIAL GENERAL LIABILITY INSURANCE (BUSINESS DEVELOPMENT INITIATIVE). (REV 4-10-15) (FA 7-31-15) (7-22) Changes to: 7-13.2 |
| Use with the approval of the District Program Management Office. Use with SP0020100BDI, SP0030201BDI, and SP0080100BDI. |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC -CSXT RAILROAD INSURANCE REQUIREMENTS (REV 5-4-20) (FA 8-24-20) (7-22) Changes to: 7-13.3. |
| When requested by the District Rail Office. |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - WAGE RATES FOR FEDERAL-AID PROJECTS. (REV 9-1-17) (FA 10-31-17) (7-22) Insert Information Required. Changes to: 7-16. |
| All Federal Aid Jobs |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS. (REV 4-25-02) (FA 7-17-02) (7-22) Changes to: Section 7. |
| Non-Federal Aid Projects |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PREFERENCE TO STATE RESIDENTS. (REV 1-13-12) (7-22) Changes to: Section 7. |
| Non-Federal Aid Projects. Construction Projects Only. |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - E-VERIFY. (REV 6-13-11) (FA 6-16-11) (7-22) Changes to: Section 7. |
| All Jobs |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - SCRUTINIZED COMPANIES. (REV 3-22-18) (7-22) Changes to: Section 7. |
| All Jobs |
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - TITLE VI ASSURANCE - DOT 1050.2, APPENDIX A and APPENDIX E. (REV 5-27-16) (FA 6-2-16) (7-22) Changes to: Section 7. |
| All Federally Funded Jobs |
PROSECUTION AND PROGRESS - SUBLETTING OR ASSIGNING OF CONTRACTS (BUSINESS DEVELOPMENT INITIATIVE). (REV 10-3-19) (FA 11-25-19) 7-22) Changes to: 8-1. |
| Use with the approval of the District Program Management Office. Use with SP0020100BDI, SP0030201BDI, and SP0071302BDI. |
PROSECUTION AND PROGRESS - PROSECUTION OF WORK (SUBMISSION OF WORKING SCHEDULE). (REV 5-20-21) (FA 7-7-21) (7-22) Changes to: 8-3.2. |
| Use only when CPM is authorized by District Construction Engineer. |
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (FLEXIBLE START TIME). (REV 3-2-17) (FA 4-27-17) (7-22) Insert Information Required Changes to: 8-3.3. |
| When called for by the District Construction Engineer or the District Maintenance Engineer/Administrator. *Contracts Office must be notified. |
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (NOTICE TO PROCEED). (REV 3-2-17) (FA 4-27-17) (7-22) Insert Information Required Changes to: 8-3.3. |
| When called for by the District Construction Engineer. Use with the approval of the Chief Engineer. |
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (MANDATORY START DATE). (REV 3-2-17) (FA 4-27-17) (7-22) Insert Information Required. Changes to: 8-3.3. |
| When called for by the District Construction Engineer. Use with the approval of the Chief Engineer. *Contracts Office must be notified. |
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - PARTNERING. (REV 5-15-12) (FA 5-21-12) (7-22) Insert Information Required. Changes to: 8-3. |
| 999-16 *Contracts Office must be notified. |
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - DISPUTES REVIEW BOARD. (REV 6-27-19) (FA 7-31-19) (7-22) Changes to: 8-3. |
| 999-20 Items *Contracts Office must be notified. |
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - REGIONAL DISPUTES REVIEW BOARD. (REV 6-27-19) (FA 7-31-19) (7-22) Changes to: 8-3. |
| Jobs without 999-20 Items |
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - STATEWIDE DISPUTES REVIEW BOARD. (REV 6-27-19 ) (FA 8-14-19) (7-22) Changes to: 8-3. |
| 334, 337, 350, 570, or 649 Items |
PROSECUTION AND PROGRESS – COMPUTATION OF CONTRACT TIME – ADJUSTING CONTRACT TIME – INCREASED WORK (LUMP SUM). (REV 8-1-00) (7-22) Changes to: 8-4.1, 8-7.3.1. |
| Lump Sum Projects |
PROSECUTION AND PROGRESS – LIMITATIONS OF OPERATIONS – NIGHT WORK ALONG COASTAL ROADS. (REV 4-8-19) (FA 7-22-19) (7-22) Changes to: 8-4.1 |
| Use when requested by the District Environmental Office |
PROSECUTION AND PROGRESS - LIMITATIONS OF OPERATIONS - FENCING. (REV 6-17-04) (FA 7-13-04) (7-22) Changes to: 8-4.8. |
| Jobs on Limited Access Highways |
PROSECUTION AND PROGRESS - LIMITATIONS OF OPERATIONS - CONTAMINATED MATERIAL (MERCURY-CONTAINING DEVICES AND LAMPS). (REV 11-6-95) (FA 12-27-95) (7-22) Insert Information Required. Changes to: 8-4.9. |
| Jobs with Lighting |
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (REDUCED PRODUCTIVITY). (REV 12-22-98) (FA 1-19-99) (7-22) Insert Information Required. Changes to: 8-7.1. |
| Use with approval of the District Construction Engineer. |
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (A+B BIDDING). (REV 7-24-96) (FA 9-3-96) (7-22) Changes to: 8-7.1. |
| A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030100AB,SP0030203AB, and SP0081300AB. |
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (SHORTENED CONTRACT TIME). (REV 2-14-94) (7-22) Insert Information Required. Changes to: 8-7.1. |
| Use with the approval of the Chief Engineer. |
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (HIGHER PRODUCTION RATES). (REV 4-2-19) (FA 9-23-19) (7-22) Changes to: 8-7.1. |
| Use when requested by the District Construction Engineer. |
PROSECUTION AND PROGRESS - LIQUIDATED DAMAGES FOR FAILURE TO COMPLETE THE WORK. (REV 5-2-17) (FA 6-20-17) (7-22) Insert Information Required. Changes to: Section 8-10.1, 8-10-2. |
| Use on all revenue producing projects. |
PROSECUTION AND PROGRESS - DAMAGE RECOVERY (USER COST). (REV 8-7-17) (7-22) Insert Information Required. Changes to: 8-12. |
| Use when requested by the District Construction Engineer. (Do not use with Lane Rental) |
PROSECUTION AND PROGRESS - ALTERNATIVE BIDDING. (REV 7-28-97) (7-22) Changes to: Section 8. |
| All Jobs with Alternative Bidding. Use with the approval of the District Construction Engineer. |
8-13. INCENTIVE - DISINCENTIVE FOR A+B. (REV 7-27-04) (FA 7-28-04) (7-22) Insert Information Required. Changes to: 8-13. |
| A+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030100AB, SP0030203AB, and SP0080701AB. |
8-13. "BONUS" PAYMENT AND WAIVER OF CONTRACTOR CLAIMS. (REV 5-19-04) (FA 7-13-04) (7-22) Insert Information Required. Changes to: 8-13. |
| A+B Jobs with Bonus Use with the approval of the District Construction Engineer. |
8-13. " BONUS " PAYMENT AND WAIVER OF CONTRACTOR CLAIMS. (REV 7-27-04) (FA 7-28-04) (7-22) Insert Information Required. Changes to: 8-13. |
| Bonus (Date Specific) Use with the approval of the District Construction Engineer. |
8-13. "BONUS" PAYMENT AND WAIVER OF CONTRACTOR CLAIMS. (REV 7-27-04) (FA 7-28-04) (7-22) Insert Information Required. Changes to: 8-13. |
| Bonus (Calendar Days) Use with the approval of the District Construction Engineer. |
8-13.INCENTIVE - DISINCENTIVE. (REV 7-27-04) (FA 7-28-04) (7-22) Insert Information Required. Changes to: 8-13. |
| Incentive - Disincentive. Use with the approval of the District Construction Engineer. Do not use with SP0081300MID. |
8-13.INCENTIVE - DISINCENTIVE FOR LANE RENTAL DAYS. (REV 9-25-03) (FA 12-24-03) (7-22) Insert Information Required. Changes to: 8-13. |
| Incentive-Disincentive for Lane Rental Days. Use with the approval of the District Construction Engineer. Do not use with SP0081300LR or SP0081300LRDR. |
8-13. LIQUIDATED SAVINGS FOR EARLY COMPLETION. (REV 5-18-99) (FA 6-10-99) (7-22) Insert Information Required. Changes to: 8-13. |
| Liquidated Savings. Use with the approval of the District Construction Engineer. |
8-13. PAY ADJUSTMENT FOR FEWER-MORE LANE RENTAL DAYS. (REV 4-29-97) (FA 5-7-97) (7-22) Changes to: 8-13. |
| Lane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0030100LR, and SP0081300LRDR. |
8-13. DAMAGE RECOVERY. (REV 9-25-03) (FA 12-24-03) (7-22) Insert Information Required. Changes to: 8-13. |
| Lane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0030100LR, and SP0081300LR. |
8-13. “BONUS” PAYMENT AND WAIVER OF CONTRACTOR CLAIMS. (REV 4-12-06) (FA 4-25-06) (7-22) Insert Information Required. Changes to: 8-13. |
| Milestone Bonus Use with the approval of the District Construction Engineer. Do not use with SP0081300B or SP0081300BCD. |
8-13. INCENTIVE - DISINCENTIVE. (REV 2-9-06) (FA 4-25-06) (7-22) Insert Information Required. Changes to: 8-13. |
| Milestone Incentive-Disincentive. Use with the approval of the District Construction Engineer. Do not use with SP0081300ID. |
MEASUREMENT AND PAYMENT (LUMP SUM). (REV 7-1-21) (FA 7-28-21) (7-22) Changes to: 9-1.3, 9-2, 9-3, 9-5.5.2, 9-11. |
| Lump Sum Projects |
MOBILIZATION (LUMP SUM) (REV 12-13-18) (FA 1-23-19) (7-22) |
| Lump Sum Projects |
CLEARING AND GRUBBING - REMOVAL OF EXISTING BRIDGES - GENERAL. (REV 9-10-07) (FA 2-15-08) (7-22) Insert Information Required. Changes to: 110-6.1. |
| Use when requested by the District Construction Engineer. Must have signed agreement from the Local Agency receiving the material. |
CLEARING AND GRUBBING - REMOVAL OF EXISTING BRIDGES - ASBESTOS CONTAINING MATERIALS (ACM) IDENTIFIED PRIOR TO THE WORK. (REV 11-10-16) (FA 1-26-17) (7-22) Changes to: 110-6. |
| Use when areas of Asbestos Abatement are identified in the Plans. |
CLEARING AND GRUBBING (MATERIAL FOR REEF ESTABLISHMENT). (REV 7-10-95) (FA 6-21-99) (7-22) Changes to: 110-11.7, 110-12.7. |
| 110-84 |
EXCAVATION AND EMBANKMENT - DESCRIPTION - IDENTIFIED AREAS OF CONTAMINATION. (REV 11-10-16) (FA 1-26-17 ) (7-22) Changes to: 120-1. |
| Use when contaminated areas are delineated in the Plans. |
MILLING OF EXISTING ASPHALT PAVEMENT. (REV 8-31-99) (FA 2-14-00) (7-22) Insert Information Required. Changes to: 327-1, 327-6. |
| When the Plans provide a location for stockpiling milled material. Insert quantity to be retained. Use "all, tons, square yards", etc. |
MILLING OF EXISTING ASPHALT PAVEMENT - EQUIPMENT. (REV 12-1-93) (7-22) Changes to: 327-2. |
| Use when requested by the District. |
MILLING OF EXISTING ASPHALT PAVEMENT (REV 12-16-19) (FA 12-30-19) (7-22) Changes to: 327-3. |
| Use with approval from the District Construction Engineer. |
HOT MIX ASPHALT - GENERAL CONSTRUCTION REQUIREMENTS. (REV 2-22-18) (FA 2-22-18) (7-22) Changes to: 330-8.2, 330-9.4, 330-9.5. |
| Use on all interstate and limited access asphalt pavement roadway projects. |
SUPERPAVE ASPHALT CONCERTE. (REV 5-4-21) (FA 7-14-21) (7-22) Changes to: 334-2.3.4. |
| Use on projects with available coring data. |
CEMENT CONCRETE PAVEMENT (COLORED CONCRETE). (REV 5-11-16) (FA 5-12-16) (7-22) Changes to: 350-1, 350-2, 350-10. |
| Use when the Plan pay item 350-30 or Colored Concrete is included. |
INTEGRAL PILE AND COLUMN JACKETS. (REV 17-22-19) (FA 1-27-20) (7-22) Changes to: 457. |
| 457 Items |
LANDSCAPING. (REV 10-30-19) (FA 1-7-20) (7-22) Changes to: 580. |
| Non-Federal Aid Jobs with Landscaping. Use when requested by the DDE. |
LANDSCAPING. (REV 5-11-21) (FA 7-14-21) (7-22) Changes to: 580. |
| All Federal Aid Jobs with Landscaping. Use when requested by the DDE. |
TREE AND PALM RELOCATION - CONSTRUCTION. | Jobs with Tree and Palm Relocation. | |
ELECTRICAL POWER SERVICE ASSEMBLIES - DESCRIPTION (Contribution-in-Aid-of Construction). (REV 6-12-18) (FA 7-2-18) (7-22) Changes to 639. |
| Use with approval of the District Utility Administrator. |
HIGHWAY ADVISORY RADIO. (REV 10-16-15) (FA 12-31-15) (7-22) |
| Use with the approval of the Chief Engineer. |
Supplemental Specifications | SS0000001 | Usage Note |
Appendices | XAPENDIC | Usage Note |
TECHNICAL SPECIAL PROVISIONS. The following Technical Special Provisions are individually signed and sealed but are included as part of this Specifications Package. |
| Jobs with TSPs. |