July 2019 Workbook


Implemented Modifications to the 2019 Standard Specifications

July 2019 Workbook

for Lettings Effective July - December 2019


Special Provisions - Specific clauses adding to or revising the Standard Specifications, setting forth conditions varying from or additional to the Standard Specifications for a specific project.

Supplemental Specifications - Additions or revisions to the Standard Specifications.

History of Revisions - To review the History of revisions for this Workbook.

 Mandatory Revisions - Critical modifications implemented for the Workbook.




Note: These files are in Adobe Acrobat (PDF) format.

File size ranges from 9 kb to 200 kb.

SPECIAL PROVISIONSSP0000001Usage Note
PROPOSAL REQUIREMENTS AND CONDITIONS (BUSINESS DEVELOPMENT INITIATIVE).
(REV 4-21-16) (FA 4-21-16) (7-19)

Changes to: 2-1, 2-7.
SP0020100BDIUse with the approval of the District Program Management Office.
Use with SP0030201BDI, SP0071302BDI and SP0080100BDI.
PROPOSAL REQUIREMENTS AND CONDITIONS - EXAMINATION OF PLANS, SPECIFICATIONS, SPECIAL PROVISIONS, AND SITE OF WORK.
(REV 11-3-15) (FA 1-27-16) (7-19)

Insert Information Required.
Changes to: 2-4.
SP0020400All Jobs (add a phone number or email address)
Do not use withSP0020400-60day
PROPOSAL REQUIREMENTS AND CONDITIONS - EXAMINATION OF PLANS, SPECIFICATIONS, SPECIAL PROVISIONS, AND SITE OF WORK (60 DAY AD).
(REV 4-11-16) (FA 7-1-16) (7-19)

Insert Information Required.
Changes to: 2-4.
SP0020400-60dayJobs with 60-day Ads. (add a phone number or email address)
Do not use withSP0020400
PROPOSAL REQUIREMENTS AND CONDITIONS - PREPARATION OF PROPOSALS (A+B BIDDING).
(REV 6-22-04) (FA 7-13-04) (7-19)

Changes to: 2-5.1.
SP0020501ABA+B Bidding. Use with the approval of the District Construction Engineer.
Use with SP0030100AB, SP0030203AB,SP0080701AB and SP0081300AB.
PROPOSAL REQUIREMENTS AND CONDITIONS - PREPARATION OF PROPOSALS (LANE RENTAL).
(REV 2-21-05) (FA 3-31-05) (7-19)

Insert Information Required.
Changes to: 2-5.1.
SP0020501LRLane Rental. Use with the approval of the District Construction Engineer.
Use with SP0030100LR, SP0081300LRDR and SP0081300LR.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS - SCOPE ALTERNATES.
(REV 11-3-15) (FA 11-20-15) (7-19)

Changes to: 3-1.
SP0030100Use at the direction of the District Construction Engineer in accordance with the Work Program Instructions.
*Notify Contracts Office on Transmittal Memo.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (A+B BIDDING).
(REV 11-5-97) (FA 1-20-98) (7-19)

Insert Information Required
Changes to: 3-1.
SP0030100ABA+B Bidding. Use with the approval of the District Construction Engineer.
Use with SP0020501AB, SP0030203AB, SP0080701AB and SP0081300AB.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (BUDGETARY CONSTRAINTS).
(REV 11-3-15) (FA 11-20-15) (7-19)

Insert Information Required
Changes to: 3-1.
SP0030100BCUse at the direction of the District Construction Engineer in accordance with the Work Program Instructions.
*Notify the Contracts Administration Office on the Transmittal Memo.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (LANE RENTAL).
(REV 11-3-15) (FA 11-20-15) (7-19)

Changes to: 3-1.
SP0030100LRLane Rental. Use with the approval of the District Construction Engineer.
Use with SP0020501LR, SP0081300LR and SP0081300LRDR.
AWARD AND EXECUTION OF CONTRACT - CONSIDERATION OF BIDS (LUMP SUM).
(REV 8-1-00) (7-19)

Changes to: 3-1.
SP0030100LSLump Sum Projects
AWARD AND EXECUTION OF CONTRACT (TIMEFRAME MODIFICATION).
(REV 3-2-17) (FA 4-27-17) (7-19)

Insert Information Required
Changes to: 3-2, 3-6, 3-7.
SP0030200Use when modifying the “Award and Execution” timeframes in the Standard Specifications.
*Contracts Office must approve.
AWARD AND EXECUTION OF CONTRACT (BUSINESS DEVELOPMENT INITIATIVE).
(REV 5-13-15) (FA 7-13-15)(7-19)

Changes to: 3-2.1, 3-2.2, 3-6, 3-7.
SP0030201BDIUse with the approval of the District Program Management Office.
Use with SP0020100BDI, SP0071302BDI, and SP0080100BDI.
AWARD AND EXECUTION OF CONTRACT - AWARD OF CONTRACTS (A+B BIDDING)
(REV 8-22-96) (FA 9-3-96) (7-19)

Insert Information Required
Changes to: 3-2.
SP0030203ABA+B Bidding. Use with the approval of the District Construction Engineer.
Use with SP0020501AB, SP0030100AB, SP0080701AB, and SP0081300AB.
AWARD AND EXECUTION OF CONTRACT - PUBLIC RECORDS
(REV 10-17-16) (FA 10-24-16 ) (7-19)

Changes to: 3-9.
SP0030900All Jobs.
SCOPE OF THE WORK - INTENT OF CONTRACT.
(REV 8-19-09) (FA 8-24-09) (7-19)

Insert Information Required.
Changes to: 4-1.
SP0040100All Jobs, excluding Lump Sum.
SCOPE OF THE WORK (LUMP SUM).
(REV 6-3-16) (FA 6-9-16) (7-19)

Insert Information Required.
Changes to: 4-1, 4-3.1, 4-3.4, 4-3.9.4.
SP0040100LSLump Sum Projects
CONTROL OF THE WORK (LUMP SUM).
(REV 3-15-02) (7-19)

Changes to: 5-1.1, 5-2, 5-7.6.
SP0050101LSLump Sum Projects
CONTROL OF THE WORK - GENERAL INSPECTION REQUIREMENTS - COOPERATION BY THE CONTRACTOR.
(REV 2-10-94) (7-19)


Changes to: 5-9.1
SP0050901Long bridge jobs (1500 feet or longer); modify to suit.
CONTROL OF MATERIALS - ACCEPTANCE CRITERIA (LUMP SUM).
(REV 8-17-09) (FA 8-24-09) (7-19)

Changes to: 6-1.
SP0060100LSLump Sum Projects
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED (COMPLIANCE WITH FHWA 1273).
(REV 1-2-14) (1-16-14) (7-19)

Changes to: 7-1.1.
SP0070101All Federal Aid Jobs
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BEAR).
(REV 6-6-17) (FA 6-13-17) (7-19)

Changes to: 7-1.4.
SP0070104-1Use when called for by the District Environmental Permit Office (Bear)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (EAGLE).
(REV 6-16-17) (FA 6-28-17) (7-19)

Changes to: 7-1.4.
SP0070104-2Use when called for by the District Environmental Permit Office (Eagle)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (GOPHER TORTOISE).
(REV 6-15-17) (FA 6-20-17) (7-19)

Changes to: 7-1.4.
SP0070104-3Use when called for by the District Environmental Permit Office (Gopher Tortoise)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (MANATEE).
(REV 6-15-17) (FA 6-20-17) (7-19)

Changes to: 7-1.4.
SP0070104-4Use when called for by the District Environmental Permit Office (Manatee)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SAWFISH).
(REV 5-25-17) (FA 6-13-17) (7-19)

Changes to: 7-1.4.
SP0070104-5Use when called for by the District Environmental Permit Office (Sawfish)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SEA TURTLE).
(REV 5-25-17) (FA 6-28-17) (7-19)

Changes to: 7-1.4.
SP0070104-6Use when called for by the District Environmental Permit Office (Sea Turtle)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (INDIGO SNAKE).
(REV 5-25-17) (FA 6-13-17) (7-19)

Changes to: 7-1.4.
SP0070104-7Use when called for by the District Environmental Permit Office (Indigo Snake)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (STURGEON).
(REV 5-25-17) (FA 6-28-17) (7-19)

Changes to: 7-1.4.
SP0070104-8Use when called for by the District Environmental Permit Office (Sturgeon)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (SEAGRASS BEDS)
(REV 10-3-18) (FA 12-11-18) (7-19)

Changed to: 7-1.4.
 SP0070104-9Used when called for by the District Environmental Permit Office (Seagrass Beds)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BATS)
(REV 12-7-18) (FA 1-4-19) (7-19)

Changed to: 7-1.4.
SP0070104-10Used when called for by the District Environmental Permit Office (Bats)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - LAWS TO BE OBSERVED - COMPLIANCE WITH FEDERAL ENDANGERED SPECIES ACT AND OTHER WILDLIFE REGULATIONS (BATS IN BRIDGES) 
(REV 12-7-18) (12-11-18) (7-19)

Changed to: 7-1.4.
SP0070104-11Used when called for by the District Environmental Permit Office (Bats in Bridges)
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PERMITS AND LICENSES (PERMITS PROCURED BY THE DEPARTMENT).
(REV 11-10-16) (FA 1-26-17) (7-19)

Changes to: 7-2.1.
SP0070201AJobs with permits procured by DOT
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - WORK OR STRUCTURES IN NAVIGABLE WATERS OF THE U.S., WATERS OF THE U.S. AND WATERS OF THE STATE (DISCHARGE TO).
(REV 6-9-15) (FA 7-22-15) (7-19)

Changes to: 7-2.2.
SP0070202When SWPPP is used. (One or more acres disturbed.)
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY (TOLL FACILITIES).
(REV 7-22-14) (FA 10-15-14) (7-19)

Changes to: 7-11.1, 7-11.2.
SP0071101-tollsUse with the approval of the District Traffic Operations Engineer.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - OPERATIONS WITHIN THE RAILROAD RIGHT-OF-WAY.
(REV 3-11-16) (FA 8-2-16) (7-19)

Changes to: 7-11.4.
SP0071104RRProjects involving CSX Transportation, NS, FEC, or operations within the South Florida Rail Corridor and the Central Florida Rail Corridor Right of Way
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - FLORIDA GAS TRANSMISSION COMPANY, LLC (FGT) FACILITIES.
(REV 4-6-16) (FA 4-20-16) (7-19)

Changes to: 7-11.5.
SP0071105FGTUse when Florida Gas Transmission Company, LLC (FGT) is within the project limits.
Use with SP0071201FGT.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - UTILITY ADJUSTMENTS (NO UTILITY WORK SCHEDULES).
(REV 2-10-94) (7-19)

Changes to: 7-11.5.3.
SP0071153AWhen there are no utility work schedules.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC - PRESERVATION OF EXISTING PROPERTY - UTILITIES - UTILITY ADJUSTMENTS (UTILITY WORK SCHEDULES).
(REV 11-10-16) (FA 1-26-17) (7-19)

Changes to: 7-11.5.3.
SP0071153BWhen there are utility work schedules.
LEGAL REQUIREMENTS AND RESPONSIBILITIES TO THE PUBLIC (FLORIDA GAS TRANSMISSION (FGT) COMPANY, LLC ENCROACHMENT AGREEMENTS).
(REV 7-28-16) (FA 7-31-15) (7-19)

Changes to: 7-12.1, 7-13.2, 7-13.4.
SP0071201FGTUse when Florida Gas Transmission Company, LLC (FGT) is within the project limits.
Use with SP0071105FGT.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - INSURANCE - COMMERCIAL GENERAL LIABILITY INSURANCE (BUSINESS DEVELOPMENT INITIATIVE).
(REV 4-10-15) (FA 7-31-15) (7-19)

Changes to: 7-13.2
SP0071302BDIUse with the approval of the District Program Management Office.
Use with SP0020100BDI, SP0030201BDI, and SP0080100BDI.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - WAGE RATES FOR FEDERAL-AID PROJECTS.
(REV 9-1-17) (FA 10-31-17) (7-19)

Insert Information Required.
Changes to: 7-16.
SP0071600All Federal Aid Jobs
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS.
(REV 4-25-02) (FA 7-17-02) (7-19)

Changes to: Section 7.
SP0072700Non-Federal Aid Projects
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - PREFERENCE TO STATE RESIDENTS.
(REV 1-13-12) (7-19)

Changes to: Section 7.
SP0072800Non-Federal Aid Projects.
Construction Projects Only.
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - E-VERIFY.
(REV 6-13-11) (FA 6-16-11) (7-19)

Changes to: Section 7.
SP0072900All Jobs
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - SCRUTINIZED COMPANIES.
(REV 3-22-18) (7-19)

Changes to: Section 7.
SP0073000All Jobs
           
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC - TITLE VI ASSURANCE - DOT 1050.2, APPENDIX A and APPENDIX E.
(REV 5-27-16) (FA 6-2-16) (7-19)

Changes to: Section 7.
SP0073100All Federally Funded Jobs
PROSECUTION AND PROGRESS - SUBLETTING OR ASSIGNING OF CONTRACTS (BUSINESS DEVELOPMENT INITIATIVE).
(REV 4-21-15) (FA 7-13-15) (7-19)

Changes to: 8-1.
SP0080100BDIUse with the approval of the District Program Management Office.
Use with SP0020100BDI, SP0030201BDI, and SP0071302BDI.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK (SUBMISSION OF WORKING SCHEDULE).
(REV 1-23-14) (FA 2-11-19) (7-19)

Changes to: 8-3.2.
SP0080302AUse only when CPM is authorized by District Construction Engineer.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (FLEXIBLE START TIME).
(REV 3-2-17) (FA 4-27-17) (7-19)

Insert Information Required
Changes to: 8-3.3.
SP0080303AWhen called for by the District Construction Engineer or the District Maintenance Engineer/Administrator.
*Contracts Office must be notified.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (NOTICE TO PROCEED).
(REV 3-2-17) (FA 4-27-17) (7-19)

Insert Information Required
Changes to: 8-3.3.
SP0080303BWhen called for by the District Construction Engineer.
Use with the approval of the Chief Engineer.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - BEGINNING WORK (MANDATORY START DATE).
(REV 3-2-17) (FA 4-27-17) (7-19)

Insert Information Required.
Changes to: 8-3.3.
SP0080303CWhen called for by the District Construction Engineer.
Use with the approval of the Chief Engineer.
*Contracts Office must be notified.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - PARTNERING.
(REV 5-15-12) (FA 5-21-12) (7-19)

Insert Information Required.
Changes to: 8-3.
SP0080306999-16
*Contracts Office must be notified.
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - DISPUTES REVIEW BOARD.
(REV 1-4-11) (FA 1-21-11) (7-19)

Changes to: 8-3.
SP0080307DRB999-20 Items
*Contracts Office must be notified.
SP is deleted and replaced with SP0080307DRB implemented by Man01 for 7-19.
 PROSECUTION AND PROGRESS - PROSECUTION OF WORK - DISPUTES REVIEW BOARD.
(REV 6-27-19)  (7-19)

Changes to: 8-3.
 SP0080307DRB 999-20 Items
*Contracts Office must be notified.
Mandatory #1
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - REGIONAL DISPUTES REVIEW BOARD.
(REV 1-4-11) (FA 1-21-11) (7-19)

Changes to: 8-3.
SP0080307RDRBJobs without 999-20 Items
PROSECUTION AND PROGRESS - PROSECUTION OF WORK - STATEWIDE DISPUTES REVIEW BOARD.
(REV 1-4-11) (FA 1-21-11) (7-19)

Changes to: 8-3.
SP0080308SDRB334, 337, 350, 570, 580 or 649 Items
PROSECUTION AND PROGRESS – COMPUTATION OF CONTRACT TIME – ADJUSTING CONTRACT TIME – INCREASED WORK (LUMP SUM).
(REV 8-1-00) (7-19)

Changes to: 8-4.1, 8-7.3.1.
SP0080401LSLump Sum Projects
PROSECUTION AND PROGRESS - LIMITATIONS OF OPERATIONS - FENCING.
(REV 6-17-04) (FA 7-13-04) (7-19)

Changes to: 8-4.8.
SP0080408Jobs on Limited Access Highways
PROSECUTION AND PROGRESS - LIMITATIONS OF OPERATIONS - CONTAMINATED MATERIAL (MERCURY-CONTAINING DEVICES AND LAMPS).
(REV 11-6-95) (FA 12-27-95) (7-19)

Insert Information Required.
Changes to: 8-4.9.
SP0080409Jobs with Lighting
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (REDUCED PRODUCTIVITY).
(REV 12-22-98) (FA 1-19-99) (7-19)

Insert Information Required.
Changes to: 8-7.1.
SP0080701AUse with approval of the District Construction Engineer.
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (A+B BIDDING).
(REV 7-24-96) (FA 9-3-96) (7-19)

Changes to: 8-7.1.
SP0080701ABA+B Bidding. Use with the approval of the District Construction Engineer.
Use with SP0020501AB, SP0030100AB,SP0030203AB, and SP0081300AB.
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (SHORTENED CONTRACT TIME).
(REV 2-14-94) (7-19)

Insert Information Required.
Changes to: 8-7.1.
SP0080701BUse with the approval of the Chief Engineer.
PROSECUTION AND PROGRESS - COMPUTATION OF CONTRACT TIME - GENERAL (HIGHER PRODUCTION RATES).
(REV 12-22-98) (FA 2-1-99) (7-19)

Changes to: 8-7.1.
SP0080701CUse when requested by the District Construction Engineer.
PROSECUTION AND PROGRESS - LIQUIDATED DAMAGES FOR FAILURE TO COMPLETE THE WORK.
(REV 5-2-17) (FA 6-20-17) (7-19)

Insert Information Required.
Changes to: Section 8-10.1, 8-10-2.
SP0081000Use on all revenue producing projects.
PROSECUTION AND PROGRESS - DAMAGE RECOVERY (USER COST).
(REV 8-7-17) (7-19)

Insert Information Required.
Changes to: 8-12.
SP0081200Use when requested by the District Construction Engineer.
(Do not use with Lane Rental)
PROSECUTION AND PROGRESS - ALTERNATIVE BIDDING.
(REV 7-28-97) (7-19)

Changes to: Section 8.
SP0081300AAll Jobs with Alternative Bidding. Use with the approval of the District Construction Engineer.
8-13. Incentive - Disincentive for A+B.
(REV 7-27-04) (FA 7-28-04) (1-13)

Insert Information Required.
Changes to: 8-13.
SP0081300ABA+B Bidding. Use with the approval of the District Construction Engineer. Use with SP0020501AB, SP0030100AB, SP0030203AB, and SP0080701AB.
8-13. "Bonus" Payment and Waiver of Contractor Claims.
(REV 5-19-04) (FA 7-13-04) (1-05)

Insert Information Required.
Changes to: 8-13.
SP0081300ABBA+B Jobs with Bonus Use with the approval of the District Construction Engineer.
8-13. " Bonus " Payment and Waiver of Contractor Claims.
(REV 7-27-04) (FA 7-28-04) (1-05)

Insert Information Required.
Changes to: 8-13.
SP0081300BBonus (Date Specific) Use with the approval of the District Construction Engineer.
8-13. "Bonus" Payment and Waiver of Contractor Claims.
(REV 7-27-04) (FA 7-28-04) (1-05)

Insert Information Required.
Changes to: 8-13.
SP0081300BCDBonus (Calendar Days) Use with the approval of the District Construction Engineer.
8-13. Incentive - Disincentive.
(REV 7-27-04) (FA 7-28-04) (1-05)

Insert Information Required.
Changes to: 8-13.
SP0081300IDIncentive - Disincentive. Use with the approval of the District Construction Engineer. Do not use with SP0081300MID.
8-13. Incentive - Disincentive for Lane Rental Days.
(REV 9-25-03) (FA 12-24-03) (7-04)

Insert Information Required.
Changes to: 8-13.
SP0081300IDLRIncentive-Disincentive for Lane Rental Days. Use with the approval of the District Construction Engineer. Do not use with SP0081300LR or SP0081300LRDR.
8-13. Liquidated Savings for Early Completion.
(REV 5-18-99) (FA 6-10-99) (7-00)

Insert Information Required.
Changes to: 8-13.
SP0081300LQSLiquidated Savings. Use with the approval of the District Construction Engineer.
8-13. Pay Adjustment For Fewer-More Lane Rental Days.
(REV 4-29-97) (FA 5-7-97) (7-00)

Changes to: 8-13.
SP0081300LRLane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0030100LR, and SP0081300LRDR.
8-13. Damage Recovery.
(REV 9-25-03) (FA 12-24-03) (7-04)

Insert Information Required.
Changes to: 8-13.
SP0081300LRDRLane Rental. Use with the approval of the District Construction Engineer. Use with SP0020501LR, SP0030100LR, and SP0081300LR.
8-13. "Bonus" Payment and Waiver of Contractor Claims.
(REV 4-12-06) (FA 4-25-06) (1-07)

Insert Information Required.
Changes to: 8-13.
SP0081300MBMilestone Bonus Use with the approval of the District Construction Engineer. Do not use with SP0081300B or SP0081300BCD.
8-13. Incentive - Disincentive.
(REV 2-9-06) (FA 4-25-06) (1-07)

Insert Information Required.
Changes to: 8-13.
SP0081300MIDMilestone Incentive-Disincentive. Use with the approval of the District Construction Engineer. Do not use with SP0081300ID.
MEASUREMENT AND PAYMENT (LUMP SUM).
(REV 11-4-16) (FA 1-6-17) (7-19)

Changes to: 9-1.3, 9-2, 9-3, 9-5.5.2, 9-11.
SP0090103LSLump Sum Projects
MOBILIZATION (LUMP SUM) 
(REV 12-13-18) (FA 1-23-19) (7-19)
SP1010000LSLump Sum Projects
CLEARING AND GRUBBING - REMOVAL OF EXISTING BRIDGES - GENERAL.
(REV 9-10-07) (FA 2-15-08) (7-19)

Insert Information Required.
Changes to: 110-6.1.
SP1100601Use when requested by the District Construction Engineer. Must have signed agreement from the Local Agency receiving the material.
CLEARING AND GRUBBING - REMOVAL OF EXISTING BRIDGES - ASBESTOS CONTAINING MATERIALS (ACM) IDENTIFIED PRIOR TO THE WORK.
(REV 11-10-16) (FA 1-26-17) (7-19)

Changes to: 110-6.
SP1100606Use when areas of Asbestos Abatement are identified in the Plans.
CLEARING AND GRUBBING (MATERIAL FOR REEF ESTABLISHMENT).
(REV 7-10-95) (FA 6-21-99) (7-19)

Changes to: 110-11.7, 110-12.7.
SP1101107110-84
EXCAVATION AND EMBANKMENT - DESCRIPTION - IDENTIFIED AREAS OF CONTAMINATION.
(REV 11-10-16) (FA 1-26-17 ) (7-19)

Changes to: 120-1.
SP1200100AUse when contaminated areas are delineated in the Plans.
MILLING OF EXISTING ASPHALT PAVEMENT.
(REV 8-31-99) (FA 2-14-00) (7-19)

Insert Information Required.
Changes to: 327-1, 327-6.
SP3270100When the Plans provide a location for stockpiling milled material. Insert quantity to be retained. Use "all, tons, square yards", etc.
MILLING OF EXISTING ASPHALT PAVEMENT - EQUIPMENT.
(REV 12-1-93) (7-19)

Changes to: 327-2.
SP3270200Use when requested by the District.
HOT MIX ASPHALT - GENERAL CONSTRUCTION REQUIREMENTS.
(REV 2-22-18) (FA 2-22-18) (7-19)

Changes to: 330-8.2, 330-9.4, 330-9.5.
SP3300802Smooth pavement, for interstate and limited access roadway projects only.
Use with the approval of the District Construction Engineer.
CEMENT CONCRETE PAVEMENT (COLORED CONCRETE).
(REV 5-11-16) (FA 5-12-16) (7-19)

Changes to: 350-1, 350-2, 350-10.
SP3500200Jobs with Colored Concrete Pavement
INTEGRAL PILE AND COLUMN JACKETS.
(REV 1-7-16) (FA 1-14-16) (7-19)

Changes to: 457.
SP4570000457 Items
LANDSCAPING.
(REV 1-9-19) (FA 2-12-19) (7-19)

Changes to: 580.
SP5800000Non-Federal Aid Jobs with Landscaping.
Use when requested by the DDE.
LANDSCAPING.
(REV 1-24-19) (FA 2-11-19) (7-19)

Changes to: 580.
SP5800000FAAll Federal Aid Jobs with Landscaping.
Use when requested by the DDE.
TREE AND PALM RELOCATION - CONSTRUCTION.
(REV 1-14-19) (FA 1-18-19) (7-19)
 SP5810000Jobs with Tree and Palm Relocation.
ELECTRICAL POWER SERVICE ASSEMBLIES - DESCRIPTION (Contribution-in-Aid-of Construction).
(REV 6-12-18) (FA 7-2-18) (7-19)

Changes to 639.
SP6390100CIACUse with approval of the District Utility Administrator.
HIGHWAY ADVISORY RADIO.
(REV 10-16-15) (FA 12-31-15) (7-19)

SP6870000Use with the approval of the Chief Engineer.

Supplemental SpecificationsSS0000001Usage Note

AppendicesXAPENDIC Usage Note
TECHNICAL SPECIAL PROVISIONS.

The following Technical Special Provisions are individually signed and sealed but are included as part of this Specifications Package.



XTSPsJobs with TSPs