State Road (SR) 9/I-95 from North of 6th Avenue South to North of SR 704/Okeechobee Boulevard Managed Lanes Project


 

Project Updates:

The project is currently progressing through the Project Development and Environment (PD&E) Study stage, it is expected to be completed by Spring 2025. Below are current project updates.

Study Overview:

The Florida Department of Transportation (FDOT) is currently conducting a PD&E Study along SR 9/I-95 from north of 6th Avenue South to north of SR 704/Okeechobee Boulevard. A PD&E Study is FDOT’s process to evaluate the social, economic, and environmental impacts associated with a planned transportation improvement project. The purpose of this project is to increase capacity by adding managed lanes in each direction and alleviate congestion at the SR 9/I-95 and SR 80/Southern Boulevard interchange. Additionally, the study will assess overall corridor capacity, modal interrelationships, and safety, to identify issues that can be addressed as part of this project.  

Purpose and Need

The main purpose of this study is to identify a recommended improvement that will increase capacity by adding managed lanes in each direction on the I-95 segment between 6th Avenue South and SR 704/Okeechobee Boulevard. It will also alleviate congestion within the vicinity of the I-95 interchange with SR 80/Southern Boulevard. Additionally, it aims to find improvements to issues that impact roadway traffic, such as capacity, modal interrelationships, and safety.

 

 

Study Area:

 

      Goals and Objectives:

  • Increase capacity/improve level of service
  • Add a second Managed Lane
  • Evaluate ingress and egress access points on a separated Managed Lanes system
  • Enhance safety and operations
  • Improve multi-modal interrelationships
  • Facilitate emergency evacuation
  • Improve I-95 with SR 80 interchange


      Project Schedule:


    Funding

    PD&E - Funded

    Design - Unfunded

    Construction - Unfunded

 


 

District Office

Steven C. Braun, District 4 Secretary

3400 W Commercial Blvd.
Fort Lauderdale, FL 33309

Tel: 954-486-1400
Fax: 954-777-4197

E-Mail Us

Study At-A-Glance

District

Four (Southeast Florida)

PD&E Study Start Date
May 2023 

 

PD&E Study Estimated Completion Date
April 2026

Cost
PD&E - Funded 
Design - Unfunded 
Construction - Unfunded 

Lengths and Limits

Approximately 6.2 miles; From SR 9/I-95 from North of 6th Avenue South to North of SR 704/Okeechobee Boulevard